Energy Projects Near You

Solar, wind and battery projects near Doncaster (DN7)

29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN7 (Doncaster): 2 are waiting for a planning decision, 19 approved but not yet running, 6 operational. The largest live scheme is Thorpe Marsh Power Station (1,450 MW battery storage, approved on 28 January 2025, not yet built), 4.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29projects within 10 km
2awaiting a decision
19approved, not running
6operational

Projects within 10 km of DN7

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Warren Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster2.5
Thorpe Marsh Power Stationbattery storagebattery storage1,450approved, not builtupdated Nov 2025Apr 2023granted Jan 2025Nov 2025Doncaster4.8
Thorpe Marsh Power Station, Marsh Lanebattery storagebattery storage1,400approved, not builtupdated Feb 2025Apr 2023granted Jan 2025Feb 2025Doncaster4.8
Ikea Distribution Centrerooftop solarrooftop solar1.7operationalupdated Jul 2016Feb 2014granted Apr 2014Jul 2016Doncaster4.8
Fenwick Solar Farm & Battery Storagesolar farmsolar farm238approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster5.0
Next Distribution Centre Doncasterrooftop solarrooftop solar2.5operationalupdated Jun 2017——Jun 2017Doncaster5.2
The Tween Bridge Solar Farmsolar farmsolar farm800application submittedupdated Oct 2025Aug 2025—Oct 2025Doncaster6.6
The Tween Bridge Solar Farmbattery storagebattery storage400application submittedupdated Oct 2025Aug 2025—Oct 2025Doncaster6.6
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storagebattery storage180approved, not builtupdated May 2024Sep 2023granted Apr 2024May 2024Doncaster6.6
Tween Bridge Windfarmwind farmwind farm44operationalupdated Aug 2012Jan 2004granted Feb 2008Aug 2012Doncaster6.7
Twin Riverswind farmwind farm28.7operationalupdated Apr 2017Jan 2004granted Jan 2009Apr 2017Doncaster7.7
Thorne Farmsolar farmsolar farm5operationalupdated Dec 2015Sep 2014granted Apr 2015Dec 2015Doncaster7.9
The Balk, Almholmebattery storagebattery storage1,025approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster8.0
The Balk, Almholme Solar Farmsolar farmsolar farm49.9approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster8.0
Cutts Bros, Wharf Roadbattery storagebattery storage50approved, not builtupdated Nov 2024May 2024granted Oct 2024Nov 2024Doncaster9.5
Aire & Calder Wind Farmwind farmwind farm45application withdrawnupdated Jun 2011Aug 2005—Jun 2011East Riding of Yorkshire9.8
Old River Don Wind Farmwind farmwind farm18refusedupdated Oct 2015Jun 2014refused Sep 2015Oct 2015North Lincolnshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Warren Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster2.5
Tudworth Field Road, Hatfieldrooftop solarrooftop solar0.3operationalupdated Apr 2022Mar 2022granted Apr 2022Apr 2022Doncaster3.3
Tudworth Field Road, Hatfieldrooftop solarrooftop solar0.2under constructionupdated Apr 2022Mar 2022granted Jul 2022Apr 2022Doncaster3.3
Jj Foodservice Limited, Derbyshire Courtrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Doncaster4.8
Fenwick Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster5.0
Aggreko UK, Sandall Stones Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster5.3
Aggreko UK, Sandall Stones Roadbattery storagebattery storage—approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster5.3
Haith Group Limited, Cow House Lanerooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Doncaster5.6
Sainsburys, Thorne Roadrooftop solarrooftop solar0.6approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Doncaster5.9
Yorkshire Way, Armthorperooftop solarrooftop solar1approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Doncaster6.4
Premier Logistics Park, Churchill Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Doncaster9.3
Greenland Hall Farm – Ground Mounted Solar Panelssolar farmsolar farm—approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023East Riding of Yorkshire10.0

Distance from the average position of the DN7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm614101,137
Rooftop solar1007302.4
Wind farm400210
Battery storage918004,505

MW in pipeline: pending, approved and under-construction capacity.

How Doncaster decides solar, wind and battery applications

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Doncaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN7, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.