Solar, wind and battery projects near Doncaster (DN4)
40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN4 (Doncaster): 1 is waiting for a planning decision, 32 approved but not yet running, 3 operational. The largest live scheme is Thorpe Marsh Power Station (1,450 MW battery storage, approved on 28 January 2025, not yet built), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DN4
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| J3 Business Parkbattery storage | battery storage | 16 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jul 2023 | Jun 2023 | Doncaster | 0.5 |
| J3 Business Parkbattery storage | battery storage | 10 | under constructionupdated Jul 2024 | Oct 2022 | granted Jan 2023 | Jul 2024 | Doncaster | 0.5 |
| Amazon LBA2 (Principal Place)rooftop solar | rooftop solar | 2 | permission expiredupdated Feb 2020 | Jul 2018 | granted Mar 2019 | Feb 2020 | Doncaster | 2.5 |
| Iport Avenue, New Rossington Solar Panelsrooftop solar | rooftop solar | 1.9 | approved, not built may be out of dateupdated May 2021 | Feb 2021 | granted Mar 2021 | May 2021 | Doncaster | 2.6 |
| Cutts Bros, Wharf Roadbattery storage | battery storage | 50 | approved, not builtupdated Nov 2024 | May 2024 | granted Oct 2024 | Nov 2024 | Doncaster | 3.1 |
| Toronto Way, New Rossington Solar Panelsrooftop solar | rooftop solar | 2.3 | approved, not built may be out of dateupdated Feb 2023 | Feb 2021 | granted Apr 2021 | Feb 2023 | Doncaster | 3.5 |
| Next Distribution Centre Doncasterrooftop solar | rooftop solar | 2.5 | operationalupdated Jun 2017 | — | — | Jun 2017 | Doncaster | 6.9 |
| Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storage | battery storage | 180 | approved, not builtupdated May 2024 | Sep 2023 | granted Apr 2024 | May 2024 | Doncaster | 6.9 |
| The Balk, Almholmebattery storage | battery storage | 1,025 | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Doncaster | 6.9 |
| The Balk, Almholme Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Doncaster | 6.9 |
| Ikea Distribution Centrerooftop solar | rooftop solar | 1.7 | operationalupdated Jul 2016 | Feb 2014 | granted Apr 2014 | Jul 2016 | Doncaster | 7.1 |
| Doncaster Road, Doncaster Roadsolar farm | solar farm | 1 | approved, not built may be out of dateupdated Jul 2023 | Dec 2022 | granted Jun 2023 | Jul 2023 | Doncaster | 7.4 |
| Marr Hall Farm, Barnsley Road Solar Farmsolar farm | solar farm | 40 | refusedupdated Jan 2026 | Jan 2024 | refused Dec 2025 | Jan 2026 | Doncaster | 7.8 |
| Marr Windfarmwind farm | wind farm | 8 | operationalupdated Mar 2012 | Dec 2006 | granted Jul 2007 | Mar 2012 | Doncaster | 8.4 |
| Partridge Hill Solar Farmsolar farm | solar farm | 33 | approved, not built may be out of dateupdated Mar 2020 | May 2015 | granted Jul 2016 | Mar 2020 | Doncaster | 8.5 |
| Fenwick Solar Farm & Battery Storagesolar farm | solar farm | 238 | approved, not builtupdated Mar 2026 | Nov 2024 | granted Feb 2026 | Mar 2026 | Doncaster | 8.5 |
| Thorpe Marsh Power Stationbattery storage | battery storage | 1,450 | approved, not builtupdated Nov 2025 | Apr 2023 | granted Jan 2025 | Nov 2025 | Doncaster | 8.7 |
| Thorpe Marsh Power Station, Marsh Lanebattery storage | battery storage | 1,400 | approved, not builtupdated Feb 2025 | Apr 2023 | granted Jan 2025 | Feb 2025 | Doncaster | 8.7 |
| Woodlandsbattery storage | battery storage | 1.2 | approved, not built may be out of dateupdated Jul 2022 | Mar 2022 | granted Jul 2022 | Jul 2022 | Doncaster | 8.9 |
| Warren Farm Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2022 | Aug 2021 | granted Mar 2022 | Feb 2022 | Doncaster | 8.9 |
| Long Lands Lanebattery storage | battery storage | 12 | abandonedupdated Feb 2019 | Oct 2017 | — | Feb 2019 | Doncaster | 8.9 |
| Croft Farm, Askern Road Solar Array & Hydrogen Plantsolar farm | solar farm | 2.5 | under constructionupdated Mar 2026 | Sep 2022 | granted May 2023 | Mar 2026 | Doncaster | 9.2 |
| Aven Industrial Estatebattery storage | battery storage | 20 | permission expiredupdated Jun 2020 | Jun 2017 | granted Jun 2018 | Jun 2020 | Rotherham | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Morris & Co Handlers, Balby Carr Bankrooftop solar | rooftop solar | 0.6 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Doncaster | 0.5 |
| Morris And Co Handlers, Balby Carr Bankrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Doncaster | 0.5 |
| Premier Logistics Park, Churchill Roadrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Doncaster | 3.1 |
| Sainsburys, Thorne Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | Doncaster | 5.4 |
| Don Valley Academy, Jossey Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Doncaster | 5.7 |
| Yorkshire Way, Armthorperooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | Doncaster | 6.0 |
| Haith Group Limited, Cow House Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Doncaster | 6.1 |
| Aggreko UK, Sandall Stones Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Doncaster | 6.4 |
| Aggreko UK, Sandall Stones Roadbattery storage | battery storage | — | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Doncaster | 6.4 |
| Jj Foodservice Limited, Derbyshire Courtrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Doncaster | 7.0 |
| Red House Solar Panelsrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2022 | Jul 2021 | granted Sep 2021 | Nov 2022 | Doncaster | 7.4 |
| Red House Farm, High Melton -Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | May 2022 | granted Sep 2022 | Nov 2022 | Doncaster | 7.4 |
| De Warenne Academy, Gardens Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Dec 2025 | Dec 2025 | Doncaster | 8.1 |
| Fenwick Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Mar 2026 | Nov 2024 | granted Feb 2026 | Mar 2026 | Doncaster | 8.5 |
| Warren Farm Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2022 | Aug 2021 | granted Mar 2022 | Feb 2022 | Doncaster | 8.9 |
| Aven Industrial Park, Tickhill Roadbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2023 | Aug 2022 | granted Sep 2022 | Feb 2023 | Rotherham | 9.5 |
| Eland House, Denabyrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated May 2022 | Apr 2022 | — | May 2022 | Doncaster | 9.6 |
Distance from the average position of the DN4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 6 | 0 | 1 | 374 |
| Rooftop solar | 18 | 1 | 14 | 2 | 0 | 8.5 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 14 | 0 | 12 | 0 | 0 | 4,132 |
MW in pipeline: pending, approved and under-construction capacity.
How Doncaster decides solar, wind and battery applications
| Applications | Doncaster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 3 (7%) | 19% |
| Solar refused | 1 of 27 | 12% |
| Onshore wind refused | 1 of 5 | 45% |
| Battery storage refused | 1 of 11 | 16% |
| Median time from submission to decision | 17.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN4, 11 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.