Energy Projects Near You

Solar, wind and battery projects near Doncaster (DN4)

40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN4 (Doncaster): 1 is waiting for a planning decision, 32 approved but not yet running, 3 operational. The largest live scheme is Thorpe Marsh Power Station (1,450 MW battery storage, approved on 28 January 2025, not yet built), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40projects within 10 km
1awaiting a decision
32approved, not running
3operational

Projects within 10 km of DN4

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
J3 Business Parkbattery storagebattery storage16approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023Doncaster0.5
J3 Business Parkbattery storagebattery storage10under constructionupdated Jul 2024Oct 2022granted Jan 2023Jul 2024Doncaster0.5
Amazon LBA2 (Principal Place)rooftop solarrooftop solar2permission expiredupdated Feb 2020Jul 2018granted Mar 2019Feb 2020Doncaster2.5
Iport Avenue, New Rossington Solar Panelsrooftop solarrooftop solar1.9approved, not built may be out of dateupdated May 2021Feb 2021granted Mar 2021May 2021Doncaster2.6
Cutts Bros, Wharf Roadbattery storagebattery storage50approved, not builtupdated Nov 2024May 2024granted Oct 2024Nov 2024Doncaster3.1
Toronto Way, New Rossington Solar Panelsrooftop solarrooftop solar2.3approved, not built may be out of dateupdated Feb 2023Feb 2021granted Apr 2021Feb 2023Doncaster3.5
Next Distribution Centre Doncasterrooftop solarrooftop solar2.5operationalupdated Jun 2017——Jun 2017Doncaster6.9
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storagebattery storage180approved, not builtupdated May 2024Sep 2023granted Apr 2024May 2024Doncaster6.9
The Balk, Almholmebattery storagebattery storage1,025approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster6.9
The Balk, Almholme Solar Farmsolar farmsolar farm49.9approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster6.9
Ikea Distribution Centrerooftop solarrooftop solar1.7operationalupdated Jul 2016Feb 2014granted Apr 2014Jul 2016Doncaster7.1
Doncaster Road, Doncaster Roadsolar farmsolar farm1approved, not built may be out of dateupdated Jul 2023Dec 2022granted Jun 2023Jul 2023Doncaster7.4
Marr Hall Farm, Barnsley Road Solar Farmsolar farmsolar farm40refusedupdated Jan 2026Jan 2024refused Dec 2025Jan 2026Doncaster7.8
Marr Windfarmwind farmwind farm8operationalupdated Mar 2012Dec 2006granted Jul 2007Mar 2012Doncaster8.4
Partridge Hill Solar Farmsolar farmsolar farm33approved, not built may be out of dateupdated Mar 2020May 2015granted Jul 2016Mar 2020Doncaster8.5
Fenwick Solar Farm & Battery Storagesolar farmsolar farm238approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster8.5
Thorpe Marsh Power Stationbattery storagebattery storage1,450approved, not builtupdated Nov 2025Apr 2023granted Jan 2025Nov 2025Doncaster8.7
Thorpe Marsh Power Station, Marsh Lanebattery storagebattery storage1,400approved, not builtupdated Feb 2025Apr 2023granted Jan 2025Feb 2025Doncaster8.7
Woodlandsbattery storagebattery storage1.2approved, not built may be out of dateupdated Jul 2022Mar 2022granted Jul 2022Jul 2022Doncaster8.9
Warren Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster8.9
Long Lands Lanebattery storagebattery storage12abandonedupdated Feb 2019Oct 2017—Feb 2019Doncaster8.9
Croft Farm, Askern Road Solar Array & Hydrogen Plantsolar farmsolar farm2.5under constructionupdated Mar 2026Sep 2022granted May 2023Mar 2026Doncaster9.2
Aven Industrial Estatebattery storagebattery storage20permission expiredupdated Jun 2020Jun 2017granted Jun 2018Jun 2020Rotherham9.6
Smaller schemes under 1 MW, mostly rooftop solar (17)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Morris & Co Handlers, Balby Carr Bankrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Doncaster0.5
Morris And Co Handlers, Balby Carr Bankrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Doncaster0.5
Premier Logistics Park, Churchill Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Doncaster3.1
Sainsburys, Thorne Roadrooftop solarrooftop solar0.6approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Doncaster5.4
Don Valley Academy, Jossey Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Doncaster5.7
Yorkshire Way, Armthorperooftop solarrooftop solar1approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Doncaster6.0
Haith Group Limited, Cow House Lanerooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Doncaster6.1
Aggreko UK, Sandall Stones Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster6.4
Aggreko UK, Sandall Stones Roadbattery storagebattery storage—approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster6.4
Jj Foodservice Limited, Derbyshire Courtrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Doncaster7.0
Red House Solar Panelsrooftop solarrooftop solar0.1approved, not builtupdated Nov 2022Jul 2021granted Sep 2021Nov 2022Doncaster7.4
Red House Farm, High Melton -Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022May 2022granted Sep 2022Nov 2022Doncaster7.4
De Warenne Academy, Gardens Lanerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Doncaster8.1
Fenwick Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster8.5
Warren Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster8.9
Aven Industrial Park, Tickhill Roadbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2023Aug 2022granted Sep 2022Feb 2023Rotherham9.5
Eland House, Denabyrooftop solarrooftop solar0.3application submitted may be out of dateupdated May 2022Apr 2022—May 2022Doncaster9.6

Distance from the average position of the DN4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm70601374
Rooftop solar18114208.5
Wind farm100100
Battery storage14012004,132

MW in pipeline: pending, approved and under-construction capacity.

How Doncaster decides solar, wind and battery applications

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Doncaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN4, 11 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.