Fenwick Solar Farm & Battery Storage (238 MW)

Fenwick Solar Farm & Battery Storage is a 238 MW solar farm project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 February 2026, not yet built; the record was last updated on 3 March 2026. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010152).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

238 MWsolar farm
approved, not builtstatus in REPD
3 March 2026record last updated
Doncastercouncil area

Planning timeline

DateStage
1 November 2024Application submitted
18 February 2026Development consent granted (Secretary of State)
18 February 2031Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
238 MW
Status (REPD)
approved, not built
Record last updated
3 March 2026
Operator or applicant
Boom Developments Limited
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010152
Site area
509.0 ha
Address (REPD)
Thorpe Marsh Substation, Barnby Dun, Doncaster
Council area (by location)
Doncaster
Time to decision
68 weeks
REPD reference
14098

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010152)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010152). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Thorpe Marsh Power Station, Marsh Lanebattery storage1,400approved, not built0.3
Thorpe Marsh Power Stationbattery storage1,450approved, not built0.3
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storage180approved, not built2.0
The Balk, Almholmebattery storage1,025approved, not built3.1
The Balk, Almholme Solar Farmsolar farm49.9approved, not built3.1
Warren Farm Solar Farm & Battery Storagesolar farm49.9approved, not built4.5
Cutts Bros, Wharf Roadbattery storage50approved, not built5.9
Askern Colliery solar farmsolar farm5operational6.6
Long Lands Lanebattery storage12abandoned8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5794, -1.0889).