Energy Projects Near You

Warren Farm Solar Farm & Battery Storage (49.9 MW)

Warren Farm Solar Farm & Battery Storage is a 49.9 MW solar farm project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 March 2022, not yet built; the record was last updated on 16 February 2022. REPD records the planning permission as expiring on 15 March 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
16 February 2022record last updated
Doncastercouncil area

REPD records the planning permission as expiring on 15 March 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
16 August 2021Application submitted
15 March 2022Planning permission granted
15 March 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2022
Operator or applicant
Enso Green Holdings I Limited
Planning authority
Doncaster
Planning application reference
21/02567/FULM
Site area
133.5 ha
Address (REPD)
Land At Warren Farm Dunsville Doncaster
Council area (by location)
Doncaster
Time to decision
30 weeks
Contracts for Difference
AR5
REPD reference
8494

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Thorpe Marsh Power Station, Marsh Lanebattery storage1,400approved, not built4.3
Thorpe Marsh Power Stationbattery storage1,450approved, not built4.3
Fenwick Solar Farm & Battery Storagesolar farm238approved, not built4.5
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storage180approved, not built5.4
The Balk, Almholme Solar Farmsolar farm49.9approved, not built6.9
The Balk, Almholmebattery storage1,025approved, not built6.9
Cutts Bros, Wharf Roadbattery storage50approved, not built7.5
The Tween Bridge Solar Farmsolar farm800application submitted8.9
Tween Bridge Windfarmwind farm44operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5621, -1.0278).