Solar, wind and battery projects near Doncaster (DN3)

31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN3 (Doncaster): 27 approved but not yet running, 3 operational. The largest live scheme is Thorpe Marsh Power Station (1,450 MW battery storage, approved on 28 January 2025, not yet built), 4.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31projects within 10 km
0awaiting a decision
27approved, not running
3operational

Projects within 10 km of DN3

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Next Distribution Centre Doncasterrooftop solarrooftop solar2.5operationalupdated Jun 2017——Jun 2017Doncaster1.9
Ikea Distribution Centrerooftop solarrooftop solar1.7operationalupdated Jul 2016Feb 2014granted Apr 2014Jul 2016Doncaster1.9
Warren Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster2.7
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storagebattery storage180approved, not builtupdated May 2024Sep 2023granted Apr 2024May 2024Doncaster4.1
Thorpe Marsh Power Stationbattery storagebattery storage1,450approved, not builtupdated Nov 2025Apr 2023granted Jan 2025Nov 2025Doncaster4.2
Thorpe Marsh Power Station, Marsh Lanebattery storagebattery storage1,400approved, not builtupdated Feb 2025Apr 2023granted Jan 2025Feb 2025Doncaster4.2
Fenwick Solar Farm & Battery Storagesolar farmsolar farm238approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster4.2
Cutts Bros, Wharf Roadbattery storagebattery storage50approved, not builtupdated Nov 2024May 2024granted Oct 2024Nov 2024Doncaster4.9
The Balk, Almholmebattery storagebattery storage1,025approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster5.3
The Balk, Almholme Solar Farmsolar farmsolar farm49.9approved, not builtupdated Oct 2024Nov 2023granted Oct 2024Oct 2024Doncaster5.3
J3 Business Parkbattery storagebattery storage16approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023Doncaster6.6
J3 Business Parkbattery storagebattery storage10under constructionupdated Jul 2024Oct 2022granted Jan 2023Jul 2024Doncaster6.6
Iport Avenue, New Rossington Solar Panelsrooftop solarrooftop solar1.9approved, not built may be out of dateupdated May 2021Feb 2021granted Mar 2021May 2021Doncaster7.2
Amazon LBA2 (Principal Place)rooftop solarrooftop solar2permission expiredupdated Feb 2020Jul 2018granted Mar 2019Feb 2020Doncaster7.4
Toronto Way, New Rossington Solar Panelsrooftop solarrooftop solar2.3approved, not built may be out of dateupdated Feb 2023Feb 2021granted Apr 2021Feb 2023Doncaster8.7
Croft Farm, Askern Road Solar Array & Hydrogen Plantsolar farmsolar farm2.5under constructionupdated Mar 2026Sep 2022granted May 2023Mar 2026Doncaster8.7
Partridge Hill Solar Farmsolar farmsolar farm33approved, not built may be out of dateupdated Mar 2020May 2015granted Jul 2016Mar 2020Doncaster9.8
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sainsburys, Thorne Roadrooftop solarrooftop solar0.6approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Doncaster1.2
Haith Group Limited, Cow House Lanerooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Doncaster1.4
Jj Foodservice Limited, Derbyshire Courtrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Doncaster1.6
Aggreko UK, Sandall Stones Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster2.0
Aggreko UK, Sandall Stones Roadbattery storagebattery storage—approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Doncaster2.0
Yorkshire Way, Armthorperooftop solarrooftop solar1approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Doncaster2.5
Warren Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2022Aug 2021granted Mar 2022Feb 2022Doncaster2.7
Fenwick Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2024granted Feb 2026Mar 2026Doncaster4.2
Premier Logistics Park, Churchill Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Doncaster4.7
Morris & Co Handlers, Balby Carr Bankrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Doncaster6.6
Morris And Co Handlers, Balby Carr Bankrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Doncaster6.6
Don Valley Academy, Jossey Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Doncaster7.5
Tudworth Field Road, Hatfieldrooftop solarrooftop solar0.3operationalupdated Apr 2022Mar 2022granted Apr 2022Apr 2022Doncaster7.8
Tudworth Field Road, Hatfieldrooftop solarrooftop solar0.2under constructionupdated Apr 2022Mar 2022granted Jul 2022Apr 2022Doncaster7.8

Distance from the average position of the DN3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm50500373
Rooftop solar16012307.8
Battery storage10010004,131

MW in pipeline: pending, approved and under-construction capacity.

How Doncaster decides solar, wind and battery applications

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Doncaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN3, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.