Energy Projects Near You

The Balk, Almholme (1,025 MW battery storage)

The Balk, Almholme is a 1,025 MW battery storage project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 October 2024, not yet built; the record was last updated on 28 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,025 MWbattery storage
approved, not builtstatus in REPD
28 October 2024record last updated
Doncastercouncil area

Planning timeline

DateStage
29 November 2023Application submitted
14 October 2024Planning permission granted
14 October 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (co-located with re)
Capacity
1,025 MW
Status (REPD)
approved, not built
Record last updated
28 October 2024
Operator or applicant
Innova Renewables
Planning authority
Doncaster
Planning application reference
23/02482/FULM
Address (REPD)
The Balk, Almholme, Doncaster
Council area (by location)
Doncaster
Time to decision
46 weeks
Name in REPD
The Balk, Almholme - Energy Storage System
REPD reference
14061

Recorded together with The Balk, Almholme Solar Farm (49.9 MW solar farm, approved, not built).

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storage180approved, not built1.4
Fenwick Solar Farm & Battery Storagesolar farm238approved, not built3.1
Thorpe Marsh Power Station, Marsh Lanebattery storage1,400approved, not built3.4
Thorpe Marsh Power Stationbattery storage1,450approved, not built3.4
Cutts Bros, Wharf Roadbattery storage50approved, not built3.9
Long Lands Lanebattery storage12abandoned5.2
Askern Colliery solar farmsolar farm5operational6.3
Marr Hall Farm, Barnsley Road Solar Farmsolar farm40refused6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5671, -1.1313).