Energy Projects Near You

Askern Colliery solar farm (5 MW)

Askern Colliery solar farm is a 5 MW solar farm project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 August 2015; the record was last updated on 3 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 November 2015record last updated
Doncastercouncil area

Planning timeline

DateStage
1 August 2014Application submitted
8 December 2014Planning permission granted
12 March 2015Construction started
14 August 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 November 2015
Operator or applicant
Anesco
Planning authority
Doncaster
Planning application reference
14/01829/FULM
Site area
14.5 ha
Address (REPD)
Land At Former Colliery, Campsall Road, Askern, Doncaster
Council area (by location)
Doncaster
Time to decision
18 weeks
REPD reference
2213

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Norton Community Wind Turbineswind farm5refused2.8
The Balk, Almholme Solar Farmsolar farm49.9approved, not built6.3
The Balk, Almholmebattery storage1,025approved, not built6.3
Fenwick Solar Farm & Battery Storagesolar farm238approved, not built6.6
Thorpe Marsh Power Stationbattery storage1,450approved, not built6.7
Thorpe Marsh Power Station, Marsh Lanebattery storage1,400approved, not built6.7
Fordtead Lane, Thorpe Marsh Battery Energy Facilitybattery storage180approved, not built6.9
Long Lands Lanebattery storage12abandoned7.0
Moorhouse Grange, Moorhouse Lane Solar Farmsolar farm30application submitted7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6208, -1.1602).