Marr Windfarm (8 MW)

Marr Windfarm is an 8 MW wind farm project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 January 2012; the record was last updated on 29 March 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
operationalstatus in REPD
29 March 2012record last updated
Doncastercouncil area

Planning timeline

DateStage
20 December 2006Application submitted
17 July 2007Planning permission granted
1 March 2011Construction started
18 January 2012Operational

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
29 March 2012
Operator or applicant
Banks Renewables
Planning authority
Doncaster
Planning application reference
07/00445/FULA
Turbines
4
Address (REPD)
Marr, South Yorkshire
Council area (by location)
Doncaster
Time to decision
30 weeks
REPD reference
3963

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Marr Hall Farm, Barnsley Road Solar Farmsolar farm40refused1.5
Long Lands Lanebattery storage12abandoned4.1
Butt Lane, Hooton Pagnell Battery Energy Storagebattery storage30application submitted4.2
Butt Lane, Hooton Pagnell Solar Farmsolar farm49.9application submitted4.2
Hampole Wind Farmwind farm8operational4.9
Moorhouse Grange, Moorhouse Lane Solar Farmsolar farm30application submitted6.2
Cutts Bros, Wharf Roadbattery storage50approved, not built7.3
Firsby Lane, Hooton Robertssolar farm13.5application submitted7.6
The Balk, Almholmebattery storage1,025approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.533, -1.2397).