Solar, wind and battery projects near Mexborough (S64)
47 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of S64 (Doncaster): 15 are waiting for a planning decision, 26 approved but not yet running, 4 operational. The largest live scheme is Whitestone Solar Farm (750 MW solar farm, application submitted on 3 July 2026, no decision recorded), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of S64
Projects of 1 MW and more (26)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Brookfields Park, Brookfields Driverooftop solar | rooftop solar | 1.1 | approved, not builtupdated Sep 2024 | Apr 2024 | granted Jun 2024 | Sep 2024 | Rotherham | 2.2 |
| Brookfields Park, Brookfields Driverooftop solar | rooftop solar | 1.1 | approved, not builtupdated Sep 2024 | Apr 2024 | granted Jun 2024 | Sep 2024 | Rotherham | 2.2 |
| Meadows Road, Manversrooftop solar | rooftop solar | 2.1 | application submitted may be out of dateupdated Feb 2022 | Feb 2022 | — | Feb 2022 | Rotherham | 3.0 |
| Firsby Lane, Hooton Robertssolar farm | solar farm | 13.5 | application submittedupdated May 2026 | May 2026 | — | May 2026 | Doncaster | 3.9 |
| Goldthorperooftop solar | rooftop solar | 1.5 | operationalupdated Jun 2014 | May 2013 | granted Jul 2013 | Jun 2014 | Barnsley | 4.5 |
| Doncaster Road, Doncaster Roadsolar farm | solar farm | 1 | approved, not built may be out of dateupdated Jul 2023 | Dec 2022 | granted Jun 2023 | Jul 2023 | Doncaster | 5.0 |
| West Melton Electricity Substationbattery storage | battery storage | 26 | approved, not built may be out of dateupdated Oct 2025 | May 2022 | granted Sep 2022 | Oct 2025 | Rotherham | 5.5 |
| Swangate Projectbattery storage | battery storage | 50 | approved, not builtupdated Jun 2022 | Jul 2017 | granted Sep 2017 | Jun 2022 | Rotherham | 5.5 |
| Cranswick Convenience Foods, Valley Park Industrial Estaterooftop solar | rooftop solar | 2.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Barnsley | 6.0 |
| Marr Windfarmwind farm | wind farm | 8 | operationalupdated Mar 2012 | Dec 2006 | granted Jul 2007 | Mar 2012 | Doncaster | 6.1 |
| Claire Court, Rawmarsh Roadbattery storage | battery storage | 40 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Rotherham | 7.2 |
| Mere Flats Solar Farmsolar farm | solar farm | 56 | approved, not built may be out of dateupdated Feb 2026 | Aug 2022 | granted May 2023 | Feb 2026 | Doncaster | 7.2 |
| Mere Flats Solar Farmbattery storage | battery storage | 16 | application submitted may be out of dateupdated Feb 2026 | Aug 2022 | — | Feb 2026 | Doncaster | 7.2 |
| Marr Hall Farm, Barnsley Road Solar Farmsolar farm | solar farm | 40 | refusedupdated Jan 2026 | Jan 2024 | refused Dec 2025 | Jan 2026 | Doncaster | 7.6 |
| Maltby Solar Farmbattery storage | battery storage | 50 | application submittedupdated Aug 2025 | Aug 2025 | — | Aug 2025 | Rotherham | 7.6 |
| Maltby Solar Farmsolar farm | solar farm | 20 | application submittedupdated Aug 2025 | Aug 2025 | — | Aug 2025 | Rotherham | 7.6 |
| Whitestone Solar Farmsolar farm | solar farm | 750 | application submittedupdated Jul 2026 | Jul 2026 | — | Jul 2026 | Rotherham | 7.6 |
| Mitchells Industrial Park, Bradberry Balk Lanebattery storage | battery storage | 26 | application withdrawnupdated Jul 2026 | Dec 2024 | — | Jul 2026 | Barnsley | 8.6 |
| Butt Lane, Hooton Pagnell Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Doncaster | 8.7 |
| Butt Lane, Hooton Pagnell Battery Energy Storagebattery storage | battery storage | 30 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Doncaster | 8.7 |
| Moat Lane, Wickersleybattery storage | battery storage | 100 | approved, not builtupdated Dec 2025 | Feb 2024 | granted Nov 2025 | Dec 2025 | Rotherham | 9.6 |
| Moat Lane, Wickersleybattery storage | battery storage | 100 | approved, not builtupdated Dec 2025 | Jul 2023 | granted Nov 2025 | Dec 2025 | Rotherham | 9.6 |
| Thurcroft Interchange Energy Parkbattery storage | battery storage | 50 | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Rotherham | 9.8 |
| Thurcroft Interchange Energy Park Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Rotherham | 9.8 |
| Hampole Wind Farmwind farm | wind farm | 8 | operationalupdated Oct 2018 | Sep 2008 | granted Dec 2009 | Oct 2018 | Doncaster | 10.0 |
| Green Lane, Thurcroftbattery storage | battery storage | 85 | approved, not built may be out of dateupdated May 2023 | Nov 2022 | granted May 2023 | May 2023 | Rotherham | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bluetree Group, Brookfields Parkrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Nov 2022 | Oct 2022 | — | Nov 2022 | Rotherham | 1.9 |
| Eland House, Denabyrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated May 2022 | Apr 2022 | — | May 2022 | Doncaster | 2.4 |
| Thrybergh Hydroelectric Schemebattery storage | battery storage | 0.3 | operationalupdated Feb 2019 | Nov 2016 | — | Feb 2019 | Rotherham | 3.1 |
| Bluetree Group, Brookfields Park Solar Photovoltaics Equipmentrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Rotherham | 3.3 |
| De Warenne Academy, Gardens Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Dec 2025 | Dec 2025 | Doncaster | 4.0 |
| Bauer Equipment, Rotary Driverooftop solar | rooftop solar | — | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Rotherham | 4.8 |
| Red House Farm, High Melton -Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | May 2022 | granted Sep 2022 | Nov 2022 | Doncaster | 5.0 |
| Red House Solar Panelsrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2022 | Jul 2021 | granted Sep 2021 | Nov 2022 | Doncaster | 5.0 |
| Aldwarke Lane - Ground Mounted Solar Arraysolar farm | solar farm | 0.8 | application submitted may be out of dateupdated Jun 2023 | Jun 2023 | — | Jun 2023 | Rotherham | 5.7 |
| Ron Hull Junior, Mangham Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Rotherham | 6.0 |
| Morrisons Supermarkets, Corton Woodrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Rotherham | 6.3 |
| Yorkshire Water Services, Ings Road Solar Panel Arraysolar farm | solar farm | 0.4 | approved, not builtupdated Nov 2025 | Oct 2023 | granted Oct 2025 | Nov 2025 | Barnsley | 7.0 |
| Naylor Industries, Station Road Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Barnsley | 7.5 |
| Whitestone Solar Farmbattery storage | battery storage | — | application submittedupdated Jul 2026 | Jul 2026 | — | Jul 2026 | Rotherham | 7.6 |
| Pearsons Assessment And Testing, Hellaby Ind Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Rotherham | 8.1 |
| Carlton Park Hotel, Moorgate Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jun 2026 | Apr 2026 | granted May 2026 | Jun 2026 | Rotherham | 8.6 |
| Moat Barn, Moat Lanesolar farm | solar farm | — | approved, not builtupdated Jul 2025 | Apr 2024 | refused Aug 2024 | Jul 2025 | Rotherham | 9.3 |
| Ickles Works, Templeborough Solar Photovoltaicsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Rotherham | 9.4 |
| Magna Way, Templeboroughbattery storage | battery storage | — | approved, not built may be out of dateupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | Rotherham | 9.7 |
| Maltby Sports Centre, Maltbyrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Rotherham | 9.7 |
| Battery Energy Storage Systembattery storage | battery storage | — | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Rotherham | 10.0 |
Distance from the average position of the S64 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 6 | 4 | 0 | 1 | 942 |
| Rooftop solar | 19 | 4 | 14 | 1 | 0 | 9.7 |
| Wind farm | 2 | 0 | 0 | 2 | 0 | 0 |
| Battery storage | 15 | 5 | 8 | 1 | 0 | 547 |
MW in pipeline: pending, approved and under-construction capacity.
How Doncaster decides solar, wind and battery applications
| Applications | Doncaster | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 3 (7%) | 19% |
| Solar refused | 1 of 27 | 12% |
| Onshore wind refused | 1 of 5 | 45% |
| Battery storage refused | 1 of 11 | 16% |
| Median time from submission to decision | 17.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near S64, 11 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.