Energy Projects Near You

Solar, wind and battery projects near Mexborough (S64)

47 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of S64 (Doncaster): 15 are waiting for a planning decision, 26 approved but not yet running, 4 operational. The largest live scheme is Whitestone Solar Farm (750 MW solar farm, application submitted on 3 July 2026, no decision recorded), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47projects within 10 km
15awaiting a decision
26approved, not running
4operational

Projects within 10 km of S64

Projects of 1 MW and more (26)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brookfields Park, Brookfields Driverooftop solarrooftop solar1.1approved, not builtupdated Sep 2024Apr 2024granted Jun 2024Sep 2024Rotherham2.2
Brookfields Park, Brookfields Driverooftop solarrooftop solar1.1approved, not builtupdated Sep 2024Apr 2024granted Jun 2024Sep 2024Rotherham2.2
Meadows Road, Manversrooftop solarrooftop solar2.1application submitted may be out of dateupdated Feb 2022Feb 2022—Feb 2022Rotherham3.0
Firsby Lane, Hooton Robertssolar farmsolar farm13.5application submittedupdated May 2026May 2026—May 2026Doncaster3.9
Goldthorperooftop solarrooftop solar1.5operationalupdated Jun 2014May 2013granted Jul 2013Jun 2014Barnsley4.5
Doncaster Road, Doncaster Roadsolar farmsolar farm1approved, not built may be out of dateupdated Jul 2023Dec 2022granted Jun 2023Jul 2023Doncaster5.0
West Melton Electricity Substationbattery storagebattery storage26approved, not built may be out of dateupdated Oct 2025May 2022granted Sep 2022Oct 2025Rotherham5.5
Swangate Projectbattery storagebattery storage50approved, not builtupdated Jun 2022Jul 2017granted Sep 2017Jun 2022Rotherham5.5
Cranswick Convenience Foods, Valley Park Industrial Estaterooftop solarrooftop solar2.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Barnsley6.0
Marr Windfarmwind farmwind farm8operationalupdated Mar 2012Dec 2006granted Jul 2007Mar 2012Doncaster6.1
Claire Court, Rawmarsh Roadbattery storagebattery storage40approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Rotherham7.2
Mere Flats Solar Farmsolar farmsolar farm56approved, not built may be out of dateupdated Feb 2026Aug 2022granted May 2023Feb 2026Doncaster7.2
Mere Flats Solar Farmbattery storagebattery storage16application submitted may be out of dateupdated Feb 2026Aug 2022—Feb 2026Doncaster7.2
Marr Hall Farm, Barnsley Road Solar Farmsolar farmsolar farm40refusedupdated Jan 2026Jan 2024refused Dec 2025Jan 2026Doncaster7.6
Maltby Solar Farmbattery storagebattery storage50application submittedupdated Aug 2025Aug 2025—Aug 2025Rotherham7.6
Maltby Solar Farmsolar farmsolar farm20application submittedupdated Aug 2025Aug 2025—Aug 2025Rotherham7.6
Whitestone Solar Farmsolar farmsolar farm750application submittedupdated Jul 2026Jul 2026—Jul 2026Rotherham7.6
Mitchells Industrial Park, Bradberry Balk Lanebattery storagebattery storage26application withdrawnupdated Jul 2026Dec 2024—Jul 2026Barnsley8.6
Butt Lane, Hooton Pagnell Solar Farmsolar farmsolar farm49.9application submittedupdated Jan 2026Dec 2025—Jan 2026Doncaster8.7
Butt Lane, Hooton Pagnell Battery Energy Storagebattery storagebattery storage30application submittedupdated Jan 2026Dec 2025—Jan 2026Doncaster8.7
Moat Lane, Wickersleybattery storagebattery storage100approved, not builtupdated Dec 2025Feb 2024granted Nov 2025Dec 2025Rotherham9.6
Moat Lane, Wickersleybattery storagebattery storage100approved, not builtupdated Dec 2025Jul 2023granted Nov 2025Dec 2025Rotherham9.6
Thurcroft Interchange Energy Parkbattery storagebattery storage50application submittedupdated Jul 2025Jun 2025—Jul 2025Rotherham9.8
Thurcroft Interchange Energy Park Solar Farmsolar farmsolar farm49.9application submittedupdated Jul 2025Jun 2025—Jul 2025Rotherham9.8
Hampole Wind Farmwind farmwind farm8operationalupdated Oct 2018Sep 2008granted Dec 2009Oct 2018Doncaster10.0
Green Lane, Thurcroftbattery storagebattery storage85approved, not built may be out of dateupdated May 2023Nov 2022granted May 2023May 2023Rotherham10.0
Smaller schemes under 1 MW, mostly rooftop solar (21)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bluetree Group, Brookfields Parkrooftop solarrooftop solar—application submitted may be out of dateupdated Nov 2022Oct 2022—Nov 2022Rotherham1.9
Eland House, Denabyrooftop solarrooftop solar0.3application submitted may be out of dateupdated May 2022Apr 2022—May 2022Doncaster2.4
Thrybergh Hydroelectric Schemebattery storagebattery storage0.3operationalupdated Feb 2019Nov 2016—Feb 2019Rotherham3.1
Bluetree Group, Brookfields Park Solar Photovoltaics Equipmentrooftop solarrooftop solar—approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Rotherham3.3
De Warenne Academy, Gardens Lanerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Doncaster4.0
Bauer Equipment, Rotary Driverooftop solarrooftop solar—application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Rotherham4.8
Red House Farm, High Melton -Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022May 2022granted Sep 2022Nov 2022Doncaster5.0
Red House Solar Panelsrooftop solarrooftop solar0.1approved, not builtupdated Nov 2022Jul 2021granted Sep 2021Nov 2022Doncaster5.0
Aldwarke Lane - Ground Mounted Solar Arraysolar farmsolar farm0.8application submitted may be out of dateupdated Jun 2023Jun 2023—Jun 2023Rotherham5.7
Ron Hull Junior, Mangham Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Rotherham6.0
Morrisons Supermarkets, Corton Woodrooftop solarrooftop solar0.4approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Rotherham6.3
Yorkshire Water Services, Ings Road Solar Panel Arraysolar farmsolar farm0.4approved, not builtupdated Nov 2025Oct 2023granted Oct 2025Nov 2025Barnsley7.0
Naylor Industries, Station Road Industrial Estaterooftop solarrooftop solar0.4approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Barnsley7.5
Whitestone Solar Farmbattery storagebattery storage—application submittedupdated Jul 2026Jul 2026—Jul 2026Rotherham7.6
Pearsons Assessment And Testing, Hellaby Ind Estaterooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Rotherham8.1
Carlton Park Hotel, Moorgate Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Rotherham8.6
Moat Barn, Moat Lanesolar farmsolar farm—approved, not builtupdated Jul 2025Apr 2024refused Aug 2024Jul 2025Rotherham9.3
Ickles Works, Templeborough Solar Photovoltaicsrooftop solarrooftop solar0.5approved, not builtupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Rotherham9.4
Magna Way, Templeboroughbattery storagebattery storage—approved, not built may be out of dateupdated May 2022Apr 2022granted Jun 2022May 2022Rotherham9.7
Maltby Sports Centre, Maltbyrooftop solarrooftop solar0.5approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Rotherham9.7
Battery Energy Storage Systembattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Rotherham10.0

Distance from the average position of the S64 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm116401942
Rooftop solar19414109.7
Wind farm200200
Battery storage155810547

MW in pipeline: pending, approved and under-construction capacity.

How Doncaster decides solar, wind and battery applications

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Doncaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near S64, 11 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.