Claire Court, Rawmarsh Road (40 MW battery storage)

Claire Court, Rawmarsh Road is a 40 MW battery storage project in Rotherham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 June 2023, not yet built; the record was last updated on 28 June 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
28 June 2023record last updated
Rotherhamcouncil area

Planning timeline

DateStage
18 April 2023Application submitted
20 June 2023Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
28 June 2023
Operator or applicant
Conrad Energy (Developments) Ii Limited
Planning authority
Rotherham
Planning application reference
RB2023/0542
Address (REPD)
Claire Court, Rawmarsh Road, Northfield
Council area (by location)
Rotherham
Time to decision
9 weeks
Name in REPD
Claire Court, Rawmarsh Road - Battery Energy Storage Facility
REPD reference
13774

Who decides

ApplicationsRotherhamUK
Decided applications (solar, wind, battery)3110,236
Refused2 (6%)19%
Solar refused1 of 1612%
Onshore wind refused0 of 345%
Battery storage refused1 of 1216%
Median time from submission to decision8.9 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Maltby Solar Farmsolar farm20application submitted0.5
Whitestone Solar Farmsolar farm750application submitted0.6
Blackburn Meadowsbattery storage10operational3.3
Brinsworth Road, Brinsworthbattery storage40application submitted4.2
Yarra Industrial Estate, Loicher Lanebattery storage20approved, not built6.3
Thurcroft Interchange Energy Parkbattery storage50application submitted6.4
Thurcroft Interchange Energy Park Solar Farmsolar farm49.9application submitted6.4
Moat Lane, Wickersleybattery storage100approved, not built6.7
Moat Lane, Wickersleybattery storage100approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4359, -1.3566).