Swangate Project (50 MW battery storage)

Swangate Project is a 50 MW battery storage project in Rotherham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 September 2017, not yet built; the record was last updated on 9 June 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
9 June 2022record last updated
Rotherhamcouncil area

Planning timeline

DateStage
24 July 2017Application submitted
22 September 2017Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
9 June 2022
Operator or applicant
Econergy International Limited
Planning authority
Rotherham
Planning application reference
RB2017/1132
Address (REPD)
Adj West Melton Electricity Substation, Elsecar Road, Brampton Bierlow
Council area (by location)
Rotherham
Time to decision
9 weeks
Name in REPD
Swangate Project - Energy Storage System
REPD reference
11437

Who decides

ApplicationsRotherhamUK
Decided applications (solar, wind, battery)3110,236
Refused2 (6%)19%
Solar refused1 of 1612%
Onshore wind refused0 of 345%
Battery storage refused1 of 1216%
Median time from submission to decision8.9 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Melton Electricity Substationbattery storage26approved, not built0.2
Mitchells Industrial Park, Bradberry Balk Lanebattery storage26application withdrawn3.8
Barnsley Battery Energy Storagebattery storage40operational6.9
Claire Court, Rawmarsh Roadbattery storage40approved, not built7.5
Yarra Industrial Estate, Loicher Lanebattery storage20approved, not built7.8
Maltby Solar Farmsolar farm20application submitted8.0
Whitestone Solar Farmsolar farm750application submitted8.1
Park Spring Wind Farmwind farm8.6operational8.2
Firsby Lane, Hooton Robertssolar farm13.5application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5018, -1.3804).