Barnsley Battery Energy Storage (40 MW)

Barnsley Battery Energy Storage is a 40 MW battery storage project in Barnsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2023; the record was last updated on 6 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
operationalstatus in REPD
6 March 2026record last updated
Barnsleycouncil area

Planning timeline

DateStage
26 January 2017Application submitted
2 August 2017Planning permission granted
1 January 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
operational
Record last updated
6 March 2026
Operator or applicant
G2 Energy / SMS Energy Services Ltd
Planning authority
Barnsley
Planning application reference
2017/0117
Address (REPD)
Land West of Hopewell Street, Stairfoot, Barnsley
Council area (by location)
Barnsley
Time to decision
27 weeks
REPD reference
20397

Who decides

ApplicationsBarnsleyUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused0 of 1312%
Onshore wind refused2 of 645%
Battery storage refused0 of 516%
Median time from submission to decision21.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mitchells Industrial Park, Bradberry Balk Lanebattery storage26application withdrawn3.2
Park Spring Wind Farmwind farm8.6operational4.2
Engine Lane, Grimethorpe Solar Farmsolar farm49.9application submitted5.4
Swangate Projectbattery storage50approved, not built6.9
West Melton Electricity Substationbattery storage26approved, not built7.0
Kirkgate Lane, Felkirksolar farm10approved, not built7.4
Manor Farm, South Hiendley Solar Photovoltaic Farmsolar farm30approved, not built7.4
Haigh Lane, Woolley Edge Lane Solar Farmsolar farm29.7approved, not built9.4
South Kirkby Business Parkbattery storage10permission expired9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5487, -1.4486).