Haigh Lane, Woolley Edge Lane Solar Farm (29.7 MW)

Haigh Lane, Woolley Edge Lane Solar Farm is a 29.7 MW solar farm project in Wakefield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 August 2025, not yet built; the record was last updated on 22 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.7 MWsolar farm
approved, not builtstatus in REPD
22 August 2025record last updated
Wakefieldcouncil area

Planning timeline

DateStage
12 January 2024Application submitted
7 August 2025Planning permission granted
7 August 2033Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
29.7 MW
Status (REPD)
approved, not built
Record last updated
22 August 2025
Operator or applicant
Boom Developments Limited
Planning authority
Wakefield
Planning application reference
23/02397/FUL
Site area
55.3 ha
Address (REPD)
Haigh Lane And Woolley Edge Lane, Wakefield
Council area (by location)
Wakefield
Time to decision
82 weeks
Name in REPD
Haigh Lane, Woolley Edge Lane - Solar Farm
REPD reference
14647

Who decides

ApplicationsWakefieldUK
Decided applications (solar, wind, battery)4510,236
Refused7 (16%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused1 of 816%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Hall Farm, New Hall Lane Solar Farmsolar farm22.4approved, not built5.5
Lady Ings Farm, Middlestown Solar Photovoltaic Farmsolar farm49.9approved, not built5.6
Low Farm, Flockton Solar Photovoltaic Farmsolar farm49.9approved, not built6.7
Manor Farm, South Hiendley Solar Photovoltaic Farmsolar farm30approved, not built7.3
Neil Fox Waybattery storage99.9application submitted7.5
Neil Fox Waybattery storage99.9application submitted7.5
Owlers Farm, Wakefield Road Solar Farmsolar farm20approved, not built8.1
Kirkgate Lane, Felkirksolar farm10approved, not built8.7
Barnsley Battery Energy Storagebattery storage40operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6154, -1.5365).