Energy Projects Near You

Manor Farm, South Hiendley Solar Photovoltaic Farm (30 MW)

Manor Farm, South Hiendley Solar Photovoltaic Farm is a 30 MW solar farm project in Wakefield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 July 2025, not yet built; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
19 August 2025record last updated
Wakefieldcouncil area

Planning timeline

DateStage
18 April 2024Application submitted
25 July 2025Planning permission granted
25 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
Enzygo Limited
Planning authority
Wakefield
Planning application reference
24/00512/FUL
Site area
38.9 ha
Address (REPD)
Manor Farm, South Hiendley, Barnsley, Wakefield
Council area (by location)
Wakefield
Time to decision
66 weeks
Name in REPD
Manor Farm, South Hiendley - Solar Photovoltaic Farm
REPD reference
12659

Who decides

ApplicationsWakefieldUK
Decided applications (solar, wind, battery)4510,236
Refused7 (16%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused1 of 816%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kirkgate Lane, Felkirksolar farm10approved, not built1.5
Engine Lane, Grimethorpe Solar Farmsolar farm49.9application submitted3.6
Park Spring Wind Farmwind farm8.6operational4.7
South Kirkby Business Parkbattery storage10permission expired6.5
Neil Fox Waybattery storage99.9application submitted6.8
Neil Fox Waybattery storage99.9application submitted6.8
Haigh Lane, Woolley Edge Lane Solar Farmsolar farm29.7approved, not built7.3
Barnsley Battery Energy Storagebattery storage40operational7.4
Cooksland Farm, Old Snydale -Battery Energy Storagebattery storage50approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.614, -1.4261).