Solar, wind and battery projects near Pontefract (WF9)
34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WF9 (Wakefield): 7 are waiting for a planning decision, 15 approved but not yet running, 6 operational. The largest live scheme is Engine Lane, Grimethorpe Solar Farm (49.9 MW solar farm, application submitted on 20 January 2025, no decision recorded), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WF9
Projects of 1 MW and more (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| South Kirkby Business Parkbattery storage | battery storage | 10 | permission expiredupdated Jan 2020 | Oct 2017 | granted Jan 2018 | Jan 2020 | Wakefield | 0.8 |
| Elmsall Way, South Elmsallrooftop solar | rooftop solar | 3 | under constructionupdated May 2022 | May 2022 | granted Sep 2022 | May 2022 | Wakefield | 3.1 |
| Finlay Beverages, Elmsall Wayrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Aug 2024 | May 2024 | granted Aug 2024 | Aug 2024 | Wakefield | 3.1 |
| Elmsall Way Warehouserooftop solar | rooftop solar | 2.4 | operationalupdated Sep 2022 | Dec 2019 | granted May 2020 | Sep 2022 | Wakefield | 3.4 |
| Moorhouse Grange, Moorhouse Lane Solar Farmsolar farm | solar farm | 30 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Doncaster | 4.4 |
| Hampole Wind Farmwind farm | wind farm | 8 | operationalupdated Oct 2018 | Sep 2008 | granted Dec 2009 | Oct 2018 | Doncaster | 5.5 |
| Kirkgate Lane, Felkirksolar farm | solar farm | 10 | approved, not builtupdated May 2025 | Sep 2023 | granted Apr 2025 | May 2025 | Wakefield | 5.5 |
| Engine Lane, Grimethorpe Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Barnsley | 5.5 |
| Park Springs, Long Roydrooftop solar | rooftop solar | 3.1 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Barnsley | 5.5 |
| Butt Lane, Hooton Pagnell Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Doncaster | 5.6 |
| Butt Lane, Hooton Pagnell Battery Energy Storagebattery storage | battery storage | 30 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Doncaster | 5.6 |
| Park Spring Wind Farmwind farm | wind farm | 8.6 | operationalupdated Nov 2015 | Oct 2013 | granted Apr 2014 | Nov 2015 | Barnsley | 6.4 |
| Manor Farm, South Hiendley Solar Photovoltaic Farmsolar farm | solar farm | 30 | approved, not builtupdated Aug 2025 | Apr 2024 | granted Jul 2025 | Aug 2025 | Wakefield | 7.0 |
| Premier Foods Bakery, Fish Dam Lane Solar Farmsolar farm | solar farm | 2 | operationalupdated Jan 2026 | Sep 2023 | granted Apr 2024 | Jan 2026 | Barnsley | 8.1 |
| Norton Community Wind Turbineswind farm | wind farm | 5 | refusedupdated Mar 2017 | Aug 2012 | refused Mar 2017 | Mar 2017 | Doncaster | 8.2 |
| Darrington Quarrywind farm | wind farm | 16 | application withdrawnupdated Jun 2016 | Dec 2010 | — | Jun 2016 | Wakefield | 8.2 |
| Goldthorperooftop solar | rooftop solar | 1.5 | operationalupdated Jun 2014 | May 2013 | granted Jul 2013 | Jun 2014 | Barnsley | 8.6 |
| Long Lands Lanebattery storage | battery storage | 12 | abandonedupdated Feb 2019 | Oct 2017 | — | Feb 2019 | Doncaster | 8.7 |
| Woodlandsbattery storage | battery storage | 1.2 | approved, not built may be out of dateupdated Jul 2022 | Mar 2022 | granted Jul 2022 | Jul 2022 | Doncaster | 8.7 |
| Lundwood, Sewage Workssolar farm | solar farm | 1.3 | approved, not builtupdated Jan 2025 | May 2023 | granted Jan 2024 | Jan 2025 | Barnsley | 8.8 |
| Pontefract Wind Farmwind farm | wind farm | 12 | refused on appealupdated Dec 2010 | May 2007 | refused Feb 2008 | Dec 2010 | Wakefield | 9.1 |
| Marr Hall Farm, Barnsley Road Solar Farmsolar farm | solar farm | 40 | refusedupdated Jan 2026 | Jan 2024 | refused Dec 2025 | Jan 2026 | Doncaster | 9.7 |
| Marr Windfarmwind farm | wind farm | 8 | operationalupdated Mar 2012 | Dec 2006 | granted Jul 2007 | Mar 2012 | Doncaster | 9.8 |
| Croft Farm, Askern Road Solar Array & Hydrogen Plantsolar farm | solar farm | 2.5 | under constructionupdated Mar 2026 | Sep 2022 | granted May 2023 | Mar 2026 | Doncaster | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Data Drive, South Kirkbyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Wakefield | 0.5 |
| Tesco Superstore, Market Streetrooftop solar | rooftop solar | 0.4 | application submitted | Apr 2026 | — | — | Wakefield | 2.3 |
| Langthwaite Road, South Kirkbysolar farm | solar farm | 0.5 | approved, not built may be out of dateupdated Jan 2022 | Dec 2021 | granted Mar 2022 | Jan 2022 | Wakefield | 2.3 |
| Upton Primary School, Waggon Lanerooftop solar | rooftop solar | 0.2 | application submittedupdated Nov 2025 | Oct 2025 | — | Nov 2025 | Wakefield | 3.2 |
| Burntwood Sports & Leisure Centre, Common Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Barnsley | 3.3 |
| Moorhouse Grange, Moorhouse Lane Battery Energybattery storage | battery storage | — | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Doncaster | 4.4 |
| Ferrymoor Way, Grimethorperooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2022 | May 2022 | granted Jul 2022 | Jun 2022 | Barnsley | 5.7 |
| Stuart Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2022 | Mar 2022 | granted Jul 2022 | Apr 2022 | Wakefield | 9.7 |
| Yorkshire Water Services, Ings Road Solar Panel Arraysolar farm | solar farm | 0.4 | approved, not builtupdated Nov 2025 | Oct 2023 | granted Oct 2025 | Nov 2025 | Barnsley | 9.8 |
| Naylor Industries, Station Road Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Barnsley | 10.0 |
Distance from the average position of the WF9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 3 | 6 | 1 | 1 | 174 |
| Rooftop solar | 12 | 2 | 8 | 2 | 0 | 9.8 |
| Wind farm | 6 | 0 | 0 | 3 | 2 | 0 |
| Battery storage | 5 | 2 | 1 | 0 | 0 | 31.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Wakefield decides solar, wind and battery applications
| Applications | Wakefield | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 9.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WF9, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.