Solar, wind and battery projects near Wakefield (WF1)
39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WF1 (Wakefield): 7 are waiting for a planning decision, 31 approved but not yet running, 1 operational. The largest live scheme is Neil Fox Way (99.9 MW battery storage, application submitted on 5 July 2022, no decision recorded; REPD status may be out of date), 2.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WF1
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Neil Fox Waybattery storage | battery storage | 99.9 | application submitted may be out of dateupdated Sep 2022 | Jul 2022 | — | Sep 2022 | Wakefield | 2.5 |
| Neil Fox Waybattery storage | battery storage | 99.9 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Wakefield | 2.5 |
| Headways, Unit 3rooftop solar | rooftop solar | 1 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | Wakefield | 4.7 |
| Owlers Farm, Wakefield Road Solar Farmsolar farm | solar farm | 20 | approved, not builtupdated Jun 2026 | May 2025 | granted May 2026 | Jun 2026 | Wakefield | 5.0 |
| Phoenix Healthcare Distribution Centrebattery storage | battery storage | 3.4 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Wakefield | 5.6 |
| Phoenix Healthcare Distribution Centrerooftop solar | rooftop solar | 3.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Wakefield | 5.6 |
| Haigh Hall Solar Farmsolar farm | solar farm | 5 | operationalupdated Jun 2017 | May 2016 | — | Jun 2017 | Leeds | 5.8 |
| Westfield Road, Carltonbattery storage | battery storage | 50 | approved, not builtupdated Jul 2025 | Nov 2023 | granted Jul 2025 | Jul 2025 | Leeds | 5.8 |
| Cooksland Farm, Old Snydale -Battery Energy Storagebattery storage | battery storage | 50 | approved, not builtupdated Mar 2026 | May 2024 | granted Nov 2025 | Mar 2026 | Wakefield | 6.4 |
| Dewsbury Sewage, Clough Lanesolar farm | solar farm | 1 | approved, not builtupdated Jun 2026 | Jul 2024 | granted May 2026 | Jun 2026 | Wakefield | 7.3 |
| Lady Ings Farm, Middlestown Solar Photovoltaic Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Apr 2025 | Dec 2021 | granted Nov 2022 | Apr 2025 | Wakefield | 7.4 |
| Haigh Lane, Woolley Edge Lane Solar Farmsolar farm | solar farm | 29.7 | approved, not builtupdated Aug 2025 | Jan 2024 | granted Aug 2025 | Aug 2025 | Wakefield | 8.5 |
| Manor Farm, South Hiendley Solar Photovoltaic Farmsolar farm | solar farm | 30 | approved, not builtupdated Aug 2025 | Apr 2024 | granted Jul 2025 | Aug 2025 | Wakefield | 9.3 |
| New Hall Farm, New Hall Lane Solar Farmsolar farm | solar farm | 22.4 | approved, not builtupdated Jun 2026 | Oct 2023 | granted Jun 2025 | Jun 2026 | Wakefield | 9.4 |
| Skelton Grange Landfill Site, Pontefract Lane Solar Farmsolar farm | solar farm | 4.4 | approved, not builtupdated Oct 2023 | Dec 2022 | granted Sep 2023 | Oct 2023 | Leeds | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Pinderfields General Hospital, Aberford Roadrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2025 | Sep 2025 | granted Oct 2025 | Dec 2025 | Wakefield | 0.6 |
| Buzz Bingo, Denby Dale Roadrooftop solar | rooftop solar | 0.1 | application submitted | Jun 2026 | — | — | Wakefield | 1.0 |
| Fieldhead Hospital, Ouchthorpe Lane Solar Carportsolar farm | solar farm | 0.3 | application submitted | Jun 2026 | — | — | Wakefield | 1.1 |
| Carshop Wakefield, Calder Island Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Wakefield | 2.8 |
| Unit 11, Albert Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated May 2023 | May 2023 | granted Jul 2023 | May 2023 | Wakefield | 3.4 |
| Arnold Clark Wakefield Motorstore, Peel Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Wakefield | 4.4 |
| Vehicle Testing Station, Patrick Greenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Wakefield | 4.6 |
| Horbury Wastewater Treatment Works, Dudfleet Lanesolar farm | solar farm | 0.3 | application submitted may be out of dateupdated Jul 2024 | Jul 2024 | — | Jul 2024 | Wakefield | 5.0 |
| Hendal Primary School, Hendal Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Wakefield | 5.1 |
| Horbury Wastewater Treatment Workssolar farm | solar farm | 0.3 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Wakefield | 5.3 |
| Ossett Health Village, Kingswayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Wakefield | 6.0 |
| DHL, Waindyke Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Wakefield | 6.4 |
| Sharpsmart, Loscoe Closerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Wakefield | 6.8 |
| Sharp Lane Primary School, Sharp Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Leeds | 7.2 |
| Clapgate Primary School, Cranmore Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Leeds | 7.3 |
| Manheim Car Auctions, Rothwellrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Leeds | 7.8 |
| Sainsburys, Railway Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Kirklees | 8.6 |
| Cockburn School, Gipsy Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Leeds | 9.1 |
| J J Food Service, Middleton Groverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Sep 2023 | Oct 2023 | Leeds | 9.3 |
| Network House, Beestonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Jan 2024 | Jan 2024 | Leeds | 9.4 |
| Calder Textiles, Dewsbury Mills Solar Photovoltaic Equipmentrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Kirklees | 9.5 |
| Steamboat Way, Glasshoughtonrooftop solar | rooftop solar | 0.8 | application submitted | Jun 2026 | — | — | Wakefield | 9.6 |
| H M Prison & Young Offender Institutionsolar farm | solar farm | 0.2 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | Wakefield | 9.7 |
| Unit G1, Whistler Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2022 | May 2022 | granted Sep 2022 | Jun 2022 | Wakefield | 9.9 |
Distance from the average position of the WF1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 3 | 8 | 1 | 0 | 159 |
| Rooftop solar | 22 | 2 | 20 | 0 | 0 | 9.3 |
| Battery storage | 5 | 2 | 3 | 0 | 0 | 303 |
MW in pipeline: pending, approved and under-construction capacity.
How Wakefield decides solar, wind and battery applications
| Applications | Wakefield | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 9.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WF1, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.