Westfield Road, Carlton (50 MW battery storage)

Westfield Road, Carlton is a 50 MW battery storage project in Leeds, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 July 2025, not yet built; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
28 July 2025record last updated
Leedscouncil area

Planning timeline

DateStage
7 November 2023Application submitted
3 May 2024Refused by the planning authority
1 November 2024Appeal lodged
14 July 2025Planning permission granted
14 July 2025Appeal allowed
14 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
28 July 2025
Operator or applicant
Firma Vogt Solar Limited
Planning authority
Leeds
Planning application reference
23/06404/FU
Appeal reference
PP/N4720/W/24/3354875
Address (REPD)
Westfield Road Carlton
Council area (by location)
Leeds
Time to decision
88 weeks
Name in REPD
Westfield Road, Carlton - Battery Storage
REPD reference
15338

Earlier applications for this site

ApplicationMWSubmittedOutcome
Westfield Road, Carlton 23/00450/FU5024 January 2023withdrawn 18 April 2023

Who decides

ApplicationsLeedsUK
Decided applications (solar, wind, battery)6810,236
Refused7 (10%)19%
Solar refused2 of 5812%
Onshore wind refused1 of 145%
Battery storage refused4 of 916%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leeds, West Yorkshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Skelton Grange Battery Storage Facilitybattery storage99approved, not built4.2
Haigh Hall Solar Farmsolar farm5operational6.0
Owlers Farm, Wakefield Road Solar Farmsolar farm20approved, not built7.8
Neil Fox Waybattery storage99.9application submitted8.0
Neil Fox Waybattery storage99.9application submitted8.0
Cooksland Farm, Old Snydale -Battery Energy Storagebattery storage50approved, not built8.4
Barnsdale Road Solar Parksolar farm40under construction8.7
Buslingthorpe Greenbattery storage49.9approved, not built8.9
Newton Lane, Ledstonbattery storage25approved, not built9.2