Buslingthorpe Green (49.9 MW battery storage)

Buslingthorpe Green is a 49.9 MW battery storage project in Leeds, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
Leedscouncil area

Planning timeline

DateStage
9 May 2024Application submitted
9 July 2025Planning permission granted
9 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Living Power Plc
Planning authority
Leeds
Planning application reference
24/02389/FU
Address (REPD)
Buslingthorpe Green, Penraevon Industrial Estate, Leeds
Council area (by location)
Leeds
Time to decision
61 weeks
Name in REPD
Buslingthorpe Green - Battery Energy Storage
REPD reference
16437

Who decides

ApplicationsLeedsUK
Decided applications (solar, wind, battery)6810,236
Refused7 (10%)19%
Solar refused2 of 5812%
Onshore wind refused1 of 145%
Battery storage refused4 of 916%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leeds, West Yorkshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Redcote Lane, Armleybattery storage60approved, not built3.1
Skelton Grange Battery Storage Facilitybattery storage99approved, not built5.4
Westfield Road, Carltonbattery storage50approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8149, -1.5437).