Energy Projects Near You

Skelton Grange Battery Storage Facility (99 MW)

Skelton Grange Battery Storage Facility is a 99 MW battery storage project in Leeds, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 August 2021, not yet built; the record was last updated on 24 January 2022. REPD also records that the planning permission expired on 4 August 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
approved, not builtmay be out of datestatus in REPD
24 January 2022record last updated
Leedscouncil area

REPD also records that the planning permission expired on 4 August 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
8 April 2021Application submitted
4 August 2021Planning permission granted
4 August 2024Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
approved, not built
Record last updated
24 January 2022
Operator or applicant
Catalyst Capital LLP
Planning authority
Leeds
Planning application reference
21/02628/FU
Address (REPD)
Former Skelton Grange Power Station Site West Road North Leeds
Council area (by location)
Leeds
Time to decision
17 weeks
REPD reference
8914

Who decides

ApplicationsLeedsUK
Decided applications (solar, wind, battery)6810,236
Refused7 (10%)19%
Solar refused2 of 5812%
Onshore wind refused1 of 145%
Battery storage refused4 of 916%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leeds, West Yorkshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Westfield Road, Carltonbattery storage50approved, not built4.2
Buslingthorpe Greenbattery storage49.9approved, not built5.4
Redcote Lane, Armleybattery storage60approved, not built7.1
Barnsdale Road Solar Parksolar farm40under construction8.6
Haigh Hall Solar Farmsolar farm5operational9.0
Newton Lane, Ledstonbattery storage25approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7779, -1.4912).