Solar, wind and battery projects near Barnsley (S70)
30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of S70 (Barnsley): 6 are waiting for a planning decision, 18 approved but not yet running, 5 operational. The largest live scheme is Swangate Project (50 MW battery storage, approved on 22 September 2017, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of S70
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Barnsley Battery Energy Storagebattery storage | battery storage | 40 | operationalupdated Mar 2026 | Jan 2017 | granted Aug 2017 | Mar 2026 | Barnsley | 1.9 |
| Lundwood, Sewage Workssolar farm | solar farm | 1.3 | approved, not builtupdated Jan 2025 | May 2023 | granted Jan 2024 | Jan 2025 | Barnsley | 3.6 |
| Mitchells Industrial Park, Bradberry Balk Lanebattery storage | battery storage | 26 | application withdrawnupdated Jul 2026 | Dec 2024 | — | Jul 2026 | Barnsley | 4.5 |
| Premier Foods Bakery, Fish Dam Lane Solar Farmsolar farm | solar farm | 2 | operationalupdated Jan 2026 | Sep 2023 | granted Apr 2024 | Jan 2026 | Barnsley | 5.4 |
| Park Spring Wind Farmwind farm | wind farm | 8.6 | operationalupdated Nov 2015 | Oct 2013 | granted Apr 2014 | Nov 2015 | Barnsley | 6.0 |
| Cranswick Convenience Foods, Valley Park Industrial Estaterooftop solar | rooftop solar | 2.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Barnsley | 6.9 |
| Park Springs, Long Roydrooftop solar | rooftop solar | 3.1 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Barnsley | 7.0 |
| Engine Lane, Grimethorpe Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Barnsley | 7.2 |
| Swangate Projectbattery storage | battery storage | 50 | approved, not builtupdated Jun 2022 | Jul 2017 | granted Sep 2017 | Jun 2022 | Rotherham | 7.6 |
| West Melton Electricity Substationbattery storage | battery storage | 26 | approved, not built may be out of dateupdated Oct 2025 | May 2022 | granted Sep 2022 | Oct 2025 | Rotherham | 7.7 |
| Sherwin Williams Diversified Brands, Thorncliffe Roadrooftop solar | rooftop solar | 1.2 | application submitted | Apr 2026 | — | — | Sheffield | 7.7 |
| Manor Farm, South Hiendley Solar Photovoltaic Farmsolar farm | solar farm | 30 | approved, not builtupdated Aug 2025 | Apr 2024 | granted Jul 2025 | Aug 2025 | Wakefield | 8.7 |
| Kirkgate Lane, Felkirksolar farm | solar farm | 10 | approved, not builtupdated May 2025 | Sep 2023 | granted Apr 2025 | May 2025 | Wakefield | 8.9 |
| Haigh Lane, Woolley Edge Lane Solar Farmsolar farm | solar farm | 29.7 | approved, not builtupdated Aug 2025 | Jan 2024 | granted Aug 2025 | Aug 2025 | Wakefield | 9.2 |
| Tofts Lane, Hunshelfbattery storage | battery storage | 40 | approved, not builtupdated May 2024 | Mar 2023 | granted Nov 2023 | May 2024 | Barnsley | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Oakwell Stadium, Grove Streetrooftop solar | rooftop solar | 0.6 | application submitted | May 2026 | — | — | Barnsley | 1.3 |
| Westgate Plaza One Solar Photovoltaic Panels & Air Source Heat Pumpsrooftop solar | rooftop solar | — | approved, not builtupdated Oct 2021 | Sep 2021 | granted Oct 2021 | Oct 2021 | Barnsley | 1.6 |
| Worsbrough Waste Water Treatment Workssolar farm | solar farm | 0.7 | application submitted may be out of dateupdated Jun 2023 | May 2023 | — | Jun 2023 | Barnsley | 1.7 |
| Stairfoot Battery Storage Facilitybattery storage | battery storage | — | operationalupdated Feb 2021 | Jan 2021 | granted Nov 2022 | Feb 2021 | Barnsley | 2.0 |
| Tesco Wombwell Lanerooftop solar | rooftop solar | 0.2 | operationalupdated Jul 2020 | Mar 2019 | granted Jul 2019 | Jul 2020 | Barnsley | 2.8 |
| Monk Bretton Service Reservoirsolar farm | solar farm | 0.4 | approved, not builtupdated Apr 2024 | Aug 2023 | granted Mar 2024 | Apr 2024 | Barnsley | 3.0 |
| Hoyland Sports Centrerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Oct 2021 | Sep 2021 | granted Oct 2021 | Oct 2021 | Barnsley | 4.7 |
| Naylor Industries, Station Road Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Barnsley | 5.5 |
| Yorkshire Water Services, Ings Road Solar Panel Arraysolar farm | solar farm | 0.4 | approved, not builtupdated Nov 2025 | Oct 2023 | granted Oct 2025 | Nov 2025 | Barnsley | 6.1 |
| Ferrymoor Way, Grimethorperooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2022 | May 2022 | granted Jul 2022 | Jun 2022 | Barnsley | 6.8 |
| Morrisons Supermarkets, Corton Woodrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Rotherham | 6.8 |
| Bauer Equipment, Rotary Driverooftop solar | rooftop solar | — | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Rotherham | 8.2 |
| Burntwood Sports & Leisure Centre, Common Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Barnsley | 9.2 |
| Bluetree Group, Brookfields Park Solar Photovoltaics Equipmentrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Rotherham | 9.6 |
| Cowley Way, Smithy Woodrooftop solar | rooftop solar | 0.1 | application submittedupdated May 2026 | Jan 2026 | — | May 2026 | Sheffield | 10.0 |
Distance from the average position of the S70 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 2 | 6 | 1 | 0 | 122 |
| Rooftop solar | 14 | 4 | 9 | 1 | 0 | 8.6 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 6 | 0 | 3 | 2 | 0 | 116 |
MW in pipeline: pending, approved and under-construction capacity.
How Barnsley decides solar, wind and battery applications
| Applications | Barnsley | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 24 | 10,236 |
| Refused | 2 (8%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 2 of 6 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 21.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near S70, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.