Twin Rivers (28.7 MW wind farm)

Twin Rivers is a 28.7 MW wind farm project in Doncaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 August 2016; the record was last updated on 26 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28.7 MWwind farm
operationalstatus in REPD
26 April 2017record last updated
Doncastercouncil area

Planning timeline

DateStage
20 January 2004Application submitted
5 January 2009Planning permission granted
15 May 2015Construction started
3 August 2016Operational

Project details

Technology
wind farm
Capacity
28.7 MW
Status (REPD)
operational
Record last updated
26 April 2017
Operator or applicant
NTR
Planning authority
Doncaster
Planning application reference
04/00505/STPLFE
Turbines
14
Address (REPD)
Moor Lane, Whitgift, East Riding of Yorkshire
Council area (by location)
Doncaster
Time to decision
259 weeks
REPD reference
3657

Who decides

ApplicationsDoncasterUK
Decided applications (solar, wind, battery)4310,236
Refused3 (7%)19%
Solar refused1 of 2712%
Onshore wind refused1 of 545%
Battery storage refused1 of 1116%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Old River Don Wind Farmwind farm18refused2.3
The Tween Bridge Solar Farmsolar farm800application submitted2.5
Tween Bridge Windfarmwind farm44operational2.6
Thorne Farmsolar farm5operational3.6
Goole Fieldswind farm32.8operational6.5
Goole Fields ll Wind Farmwind farm34.9operational7.7
Rawcliffe Bridge Wind Farmwind farm10refused8.0
Charity Farmwind farm32application withdrawn8.2
Solar Farm at Ealand Roadsolar farm49.9application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6082, -0.905).