Energy Projects Near You

Solar, wind and battery projects near Doncaster (DN9)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN9 (North Lincolnshire): 4 approved but not yet running, 3 operational. The largest live scheme is Partridge Hill Solar Farm (33 MW solar farm, approved on 29 July 2016, not yet built; REPD status may be out of date), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
4approved, not running
3operational

Projects within 10 km of DN9

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Green Lane (Westgate)solarsolar2refusedupdated Aug 2014Nov 2013refused Jul 2014Aug 2014North Lincolnshire7.5
Misson Solar Farmsolar farmsolar farm5operationalupdated Jul 2016Feb 2015granted Oct 2015Jul 2016Bassetlaw8.8
Partridge Hill Solar Farmsolar farmsolar farm33approved, not built may be out of dateupdated Mar 2020May 2015granted Jul 2016Mar 2020Doncaster9.5
Ikea Distribution Centrerooftop solarrooftop solar1.7operationalupdated Jul 2016Feb 2014granted Apr 2014Jul 2016Doncaster9.8
Next Distribution Centre Doncasterrooftop solarrooftop solar2.5operationalupdated Jun 2017——Jun 2017Doncaster9.8
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Linroyal Potato Processing Plant, Heckdykerooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Feb 2023Mar 2023North Lincolnshire8.4
Misterton PSD, Stockwith Roadsolar farmsolar farm0.4approved, not builtupdated Mar 2024Dec 2023granted Feb 2024Mar 2024Bassetlaw9.5
Yorkshire Way, Armthorperooftop solarrooftop solar1approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Doncaster9.8

Distance from the average position of the DN9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3021033.4
Rooftop solar402201.3
Solar100010

MW in pipeline: pending, approved and under-construction capacity.

How North Lincolnshire decides solar, wind and battery applications

ApplicationsNorth LincolnshireUK
Decided applications (solar, wind, battery)4710,236
Refused15 (32%)19%
Solar refused7 of 3312%
Onshore wind refused8 of 1045%
Battery storage refused0 of 416%
Median time from submission to decision10.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in North Lincolnshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN9, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.