Misson Solar Farm (5 MW)
Misson Solar Farm is a 5 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 29 July 2016.
5 MWsolar farm
operationalstatus in REPD
29 July 2016record last updated
Bassetlawcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 February 2015 | Application submitted |
| 27 October 2015 | Planning permission granted |
| 25 January 2016 | Construction started |
| 24 March 2016 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 29 July 2016
- Operator or applicant
- Novus
- Planning authority
- Bassetlaw
- Planning application reference
- 15/00215/FUL
- Site area
- 15.8 ha
- Address (REPD)
- Bawtry Road, Misson
- Council area (by location)
- Bassetlaw
- Time to decision
- 36 weeks
- REPD reference
- 6181
Who decides
| Applications | Bassetlaw | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 5 (12%) | 19% |
| Solar refused | 0 of 25 | 12% |
| Onshore wind refused | 5 of 7 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 13.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Partridge Hill Solar Farm | solar farm | 33 | approved, not built | 2.9 |
| Jubilee Farm, Barnby Moor | solar farm | 5 | operational | 9.5 |
| Chainbridge Road | solar | 8 | application withdrawn | 9.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4454, -0.981).