Misson Solar Farm (5 MW)

Misson Solar Farm is a 5 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 29 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
29 July 2016record last updated
Bassetlawcouncil area

Planning timeline

DateStage
18 February 2015Application submitted
27 October 2015Planning permission granted
25 January 2016Construction started
24 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
29 July 2016
Operator or applicant
Novus
Planning authority
Bassetlaw
Planning application reference
15/00215/FUL
Site area
15.8 ha
Address (REPD)
Bawtry Road, Misson
Council area (by location)
Bassetlaw
Time to decision
36 weeks
REPD reference
6181

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Partridge Hill Solar Farmsolar farm33approved, not built2.9
Jubilee Farm, Barnby Moorsolar farm5operational9.5
Chainbridge Roadsolar8application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4454, -0.981).