Jubilee Farm, Barnby Moor (5 MW solar farm)
Jubilee Farm, Barnby Moor is a 5 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 5 July 2017.
5 MWsolar farm
operationalstatus in REPD
5 July 2017record last updated
Bassetlawcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 31 July 2014 | Application submitted |
| 13 January 2015 | Planning permission granted |
| 15 January 2017 | Construction started |
| 15 March 2017 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 5 July 2017
- Operator or applicant
- NESF (formerly Lark Energy)
- Planning authority
- Bassetlaw
- Planning application reference
- 14/01036/FUL
- Site area
- 14.4 ha
- Address (REPD)
- Land At Jubilee Farm, Retford Road, Barnby Moor, Nottinghamshire
- Council area (by location)
- Bassetlaw
- Time to decision
- 24 weeks
- REPD reference
- 2221
Who decides
| Applications | Bassetlaw | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 40 | 10,236 |
| Refused | 5 (12%) | 19% |
| Solar refused | 0 of 25 | 12% |
| Onshore wind refused | 5 of 7 | 45% |
| Battery storage refused | 0 of 8 | 16% |
| Median time from submission to decision | 13.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bellmoor Grassland | solar | 5 | abandoned | 4.6 |
| Hundred Acre Lane, Carlton In Lindrick | solar farm | 34 | application submitted | 5.1 |
| Walkers Wood Solar Park | solar farm | 27 | operational | 6.3 |
| Tiln Farm Solar Farm | solar farm | 49.9 | under construction | 6.4 |
| Tiln Farm solar park | solar farm | 8 | operational | 7.2 |
| Little Morton Solar Farm | solar farm | 14.3 | operational | 7.4 |
| Chainbridge Road | solar | 8 | application withdrawn | 7.4 |
| Rayton Farm Lane Solar Farm | solar farm | 34 | approved, not built | 7.9 |
| Manton Wood | battery storage | 10 | permission expired | 8.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3659, -1.033).