Jubilee Farm, Barnby Moor (5 MW solar farm)

Jubilee Farm, Barnby Moor is a 5 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 5 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
5 July 2017record last updated
Bassetlawcouncil area

Planning timeline

DateStage
31 July 2014Application submitted
13 January 2015Planning permission granted
15 January 2017Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
5 July 2017
Operator or applicant
NESF (formerly Lark Energy)
Planning authority
Bassetlaw
Planning application reference
14/01036/FUL
Site area
14.4 ha
Address (REPD)
Land At Jubilee Farm, Retford Road, Barnby Moor, Nottinghamshire
Council area (by location)
Bassetlaw
Time to decision
24 weeks
REPD reference
2221

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bellmoor Grasslandsolar5abandoned4.6
Hundred Acre Lane, Carlton In Lindricksolar farm34application submitted5.1
Walkers Wood Solar Parksolar farm27operational6.3
Tiln Farm Solar Farmsolar farm49.9under construction6.4
Tiln Farm solar parksolar farm8operational7.2
Little Morton Solar Farmsolar farm14.3operational7.4
Chainbridge Roadsolar8application withdrawn7.4
Rayton Farm Lane Solar Farmsolar farm34approved, not built7.9
Manton Woodbattery storage10permission expired8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3659, -1.033).