Energy Projects Near You

Solar, wind and battery projects near Retford (DN22)

31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN22 (Bassetlaw): 6 are waiting for a planning decision, 10 approved but not yet running, 8 operational. The largest live scheme is West Burton Power Station, North Road (500 MW battery storage, approved on 5 September 2024, not yet built), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31projects within 10 km
6awaiting a decision
10approved, not running
8operational

Projects within 10 km of DN22

Projects of 1 MW and more (27)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Smeath Road Wind Turbineswind farmwind farm1refused on appealupdated Apr 2016Jul 2014refused Jul 2015Apr 2016Bassetlaw2.2
Babworth Estatewind farmwind farm1refusedupdated Jun 2014Mar 2014refused May 2014Jun 2014Bassetlaw2.3
Walmoor Farm solar parksolar farmsolar farm4operationalupdated May 2015Jan 2014granted Apr 2014May 2015Bassetlaw2.5
Tiln Farm solar parksolar farmsolar farm8operationalupdated Jun 2015Sep 2013granted Dec 2013Jun 2015Bassetlaw2.5
Tiln Farm Solar Farmsolar farmsolar farm49.9under constructionupdated Nov 2022Nov 2020granted Sep 2023Nov 2022Bassetlaw2.5
Tiln Farm Retford (extension)solar farmsolar farm1.7operationalupdated Jul 2016Mar 2015granted Jun 2015Jul 2016Bassetlaw2.7
Bellmoor Grasslandsolarsolar5abandonedupdated Dec 2015Oct 2013granted Dec 2013Dec 2015Bassetlaw3.9
Crow Holt Windfarmwind farmwind farm20refusedupdated Jul 2007Mar 2005refused Jul 2007Jul 2007Bassetlaw4.3
Chainbridge Roadsolarsolar8application withdrawnupdated Sep 2014Jan 2014—Sep 2014Bassetlaw4.8
Little Morton Solar Farmsolar farmsolar farm14.3operationalupdated Oct 2014Sep 2013granted Jan 2014Oct 2014Bassetlaw4.9
Walkers Wood Solar Parksolar farmsolar farm27operationalupdated Jun 2015May 2014granted Sep 2014Jun 2015Bassetlaw4.9
Drayton Road, Upton Solar Farmsolar farmsolar farm49.9application submittedApr 2026——Bassetlaw5.6
Wood Lane Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Nov 2024Feb 2020granted Aug 2020Nov 2024Bassetlaw5.7
Barnby Moorsolar farmsolar farm4operationalupdated Aug 2015Nov 2013granted Feb 2014Aug 2015Bassetlaw5.7
Elkesley Southbound, Elkesleybattery storagebattery storage480application submittedupdated Jul 2025Jun 2025—Jul 2025Bassetlaw6.3
West End Farm - Treswellsolar farmsolar farm16.9abandonedupdated Dec 2015Sep 2014granted Feb 2015Dec 2015Bassetlaw6.5
Jubilee Farm, Barnby Moorsolar farmsolar farm5operationalupdated Jul 2017Jul 2014granted Jan 2015Jul 2017Bassetlaw8.3
Long Ridding Lane, East Drayton Solar Farmsolar farmsolar farm49.9application submittedApr 2026——Bassetlaw8.5
West Burton Power Station, North Roadbattery storagebattery storage500approved, not builtupdated Sep 2024Dec 2022granted Sep 2024Sep 2024Bassetlaw8.6
Steeple Renewables Projectsolar farmsolar farm450application submittedupdated Oct 2025May 2025—Oct 2025Bassetlaw8.6
Steeple Renewables Projectbattery storagebattery storage150application submittedupdated Oct 2025May 2025—Oct 2025Bassetlaw8.6
Adj To The A614 Solarsolar farmsolar farm40application submitted may be out of dateupdated Apr 2024Apr 2024—Apr 2024Bassetlaw8.6
Torksey Ferry Road, Ramptonbattery storagebattery storage500approved, not builtupdated Jun 2026Dec 2024granted Jun 2026Jun 2026Bassetlaw9.0
Cottam wind farmwind farmwind farm6.9application withdrawnupdated Dec 2014Sep 2013—Dec 2014Bassetlaw9.5
Gainsborough Road, Saundbybattery storagebattery storage120under constructionupdated Jun 2026Mar 2022granted Jul 2022Jun 2026Bassetlaw9.6
Gainsborough Road, Saundby Solar Farmsolar farmsolar farm78under constructionupdated Jun 2026Mar 2022granted Jul 2022Jun 2026Bassetlaw9.6
West Burtonbattery storagebattery storage49operationalupdated Nov 2018Jul 2016—Nov 2018Bassetlaw9.7
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mansfield Road, Little Morton Farmbattery storagebattery storage—approved, not built may be out of dateupdated Jul 2022Jul 2022granted Sep 2022Jul 2022Bassetlaw4.7
Mill Hill Farm, Greenspotts Lanewind turbinewind turbine0.2approved, not builtupdated Mar 2026Oct 2025granted Feb 2026Mar 2026Bassetlaw4.9
Haughton Park Farm, West Drayton - Photovoltaic Panel Arraysrooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Bassetlaw6.7
Adj To The A614 Solarbattery storagebattery storage—approved, not builtupdated May 2026Apr 2024granted Apr 2026May 2026Bassetlaw8.6

Distance from the average position of the DN22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm154370768
Rooftop solar101000.1
Solar200000
Wind farm400030
Wind turbine101000.2
Battery storage825101,750

MW in pipeline: pending, approved and under-construction capacity.

How Bassetlaw decides solar, wind and battery applications

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Bassetlaw

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN22, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.