Energy Projects Near You

Adj To The A614 Solar (40 MW)

Adj To The A614 Solar is a 40 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 10 April 2024, no decision recorded; the record was last updated on 18 April 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
application submittedmay be out of datestatus in REPD
18 April 2024record last updated
Bassetlawcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
10 April 2024Application submitted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
application submitted
Record last updated
18 April 2024
Operator or applicant
One Planet Developments Limited
Planning authority
Bassetlaw
Planning application reference
24/00384/FUL
Site area
88.3 ha
Address (REPD)
Normanton Larches, Blyth Road, Worksop, Nottinghamshire
Council area (by location)
Bassetlaw
Name in REPD
Adj To The A614 - Solar
REPD reference
8115

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Elkesley Southbound, Elkesleybattery storage480application submitted2.4
Little Morton Solar Farmsolar farm14.3operational4.2
Walkers Wood Solar Parksolar farm27operational5.0
Manton Woodbattery storage10permission expired5.8
Netherfield Lanesolar farm19.7operational6.4
Welbeck Solar / Hazel Gapsolar farm16operational6.7
Rayton Farm Lane Solar Farmsolar farm34approved, not built6.8
Westwood Farm Solar Parksolar farm5.1operational8.0
Welbeck Collierysolar farm11.3operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.269, -1.0187).