Energy Projects Near You

Rayton Farm Lane Solar Farm (34 MW)

Rayton Farm Lane Solar Farm is a 34 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 March 2024, not yet built; the record was last updated on 20 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34 MWsolar farm
approved, not builtstatus in REPD
20 March 2024record last updated
Bassetlawcouncil area

Planning timeline

DateStage
4 December 2023Application submitted
7 March 2024Planning permission granted
7 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
34 MW
Status (REPD)
approved, not built
Record last updated
20 March 2024
Operator or applicant
Harmony Energy Limited
Planning authority
Bassetlaw
Planning application reference
23/01444/FUL
Site area
47.8 ha
Address (REPD)
The North And South Of Rayton Farm Lane
Council area (by location)
Bassetlaw
Time to decision
13 weeks
Contracts for Difference
AR6
Name in REPD
Rayton Farm Lane - Solar Farm
REPD reference
11181

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manton Woodbattery storage10permission expired1.0
Hundred Acre Lane, Carlton In Lindricksolar farm34application submitted3.8
Steeley Lane, Steetley Solar Photovoltaic Farmsolar farm18.7application submitted4.7
Walkers Wood Solar Parksolar farm27operational6.6
Adj To The A614 Solarsolar farm40application submitted6.8
Little Morton Solar Farmsolar farm14.3operational7.0
Welbeck Solar / Hazel Gapsolar farm16operational7.4
Elkesley Southbound, Elkesleybattery storage480application submitted7.7
Hunciecroft Farmsolar farm8operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3066, -1.099).