Hunciecroft Farm (8 MW solar farm)

Hunciecroft Farm is an 8 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 6 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Bassetlawcouncil area

Planning timeline

DateStage
15 August 2014Application submitted
20 November 2014Planning permission granted
1 January 2015Construction started
6 March 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
Solar century / Magnetar Solar
Planning authority
Bassetlaw
Planning application reference
14/01015/FUL
Site area
17.8 ha
Address (REPD)
Land North West Of Hunciecroft Farm Holbeck Lane Holbeck Nottinghamshire
Council area (by location)
Bassetlaw
Time to decision
14 weeks
REPD reference
2192

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Creswell Solar Parksolar farm5operational1.4
Frithwood Farm, Frithwood Lane Solar Farmsolar farm25approved, not built2.8
Steeley Lane, Steetley Solar Photovoltaic Farmsolar farm18.7application submitted4.4
Land at Bolsover Moor Quarrysolar farm5operational5.0
Welbeck Collierysolar farm11.3operational5.2
Welbeck Solar / Hazel Gapsolar farm16operational5.7
Brecks Solar Farmsolar farm45.4approved, not built6.6
Netherfield Lanesolar farm19.7operational7.2
Land West Of Sookholme Roadsolar farm10refused7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2601, -1.1878).