Energy Projects Near You

Frithwood Farm, Frithwood Lane Solar Farm (25 MW)

Frithwood Farm, Frithwood Lane Solar Farm is a 25 MW solar farm project in Bolsover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 December 2023, not yet built; the record was last updated on 20 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtstatus in REPD
20 December 2023record last updated
Bolsovercouncil area

Planning timeline

DateStage
3 January 2023Application submitted
1 December 2023Planning permission granted
1 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
20 December 2023
Operator or applicant
Elgin Energy EsCo Limited
Planning authority
Bolsover
Planning application reference
22/00583/FUL
Site area
46.0 ha
Address (REPD)
South Of Frithwood Farm Cottage Frithwood Lane Elmton
Council area (by location)
Bolsover
Time to decision
47 weeks
Name in REPD
Frithwood Farm, Frithwood Lane - Solar Farm
REPD reference
13013

Who decides

ApplicationsBolsoverUK
Decided applications (solar, wind, battery)2010,236
Refused4 (20%)19%
Solar refused2 of 1212%
Onshore wind refused2 of 245%
Battery storage refused0 of 616%
Median time from submission to decision12.5 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Creswell Solar Parksolar farm5operational1.5
Land at Bolsover Moor Quarrysolar farm5operational2.1
Hunciecroft Farmsolar farm8operational2.8
Roseland Community Wind Farmwind farm12refused5.9
Losk Lanewind farm5refused6.3
Welbeck Collierysolar farm11.3operational6.4
Land West Of Sookholme Roadsolar farm10refused6.5
Brecks Solar Farmsolar farm45.4approved, not built6.7
Steeley Lane, Steetley Solar Photovoltaic Farmsolar farm18.7application submitted6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2473, -1.2249).