Solar, wind and battery projects near Mansfield (NG19)
41 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG19 (Mansfield): 1 is waiting for a planning decision, 17 approved but not yet running, 11 operational. The largest live scheme is Hurst Farm, Mansfield Road (99.9 MW battery storage, approved on 19 December 2025, not yet built), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NG19
Projects of 1 MW and more (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Land At Debdale Lanesolar farm | solar farm | 5 | operationalupdated Aug 2016 | Jul 2015 | granted Oct 2015 | Aug 2016 | Mansfield | 1.2 |
| Littlewood Lane Solarsolar farm | solar farm | 5 | operationalupdated May 2017 | Aug 2015 | granted Nov 2015 | May 2017 | Bolsover | 2.3 |
| Penniment House Farm/Water Lane Farmsolar farm | solar farm | 4 | refusedupdated May 2016 | Feb 2016 | refused May 2016 | May 2016 | Mansfield | 2.8 |
| Ashland Solar Farmsolar farm | solar farm | 5 | permission expiredupdated Jul 2020 | Aug 2015 | granted Nov 2015 | Jul 2020 | Ashfield | 3.3 |
| Land West Of Sookholme Roadsolar farm | solar farm | 10 | refusedupdated Jun 2016 | Sep 2015 | refused Jun 2016 | Jun 2016 | Mansfield | 3.8 |
| Sherwood Way Southrooftop solar | rooftop solar | 2.7 | approved, not built may be out of dateupdated Sep 2021 | Jun 2021 | granted Sep 2021 | Sep 2021 | Ashfield | 4.0 |
| Hamilton Road Solar Farmsolar farm | solar farm | 7 | refusedupdated May 2026 | Jul 2025 | refused Mar 2026 | May 2026 | Ashfield | 4.5 |
| SPF Thirty Acres Farmsolar farm | solar farm | 3.8 | operationalupdated Jul 2016 | Jul 2015 | granted Nov 2015 | Jul 2016 | Mansfield | 5.1 |
| Lindhurst Wind Farmwind farm | wind farm | 15 | operationalupdated Dec 2010 | Jun 2006 | granted Sep 2007 | Dec 2010 | Newark and Sherwood | 5.7 |
| Brecks Solar Farmsolar farm | solar farm | 45.4 | approved, not builtupdated Feb 2026 | May 2023 | granted Sep 2023 | Feb 2026 | Mansfield | 5.7 |
| Roseland Community Wind Farmwind farm | wind farm | 12 | refusedupdated Mar 2015 | Apr 2012 | refused Jul 2013 | Mar 2015 | Bolsover | 5.8 |
| Romo, Oddicroft Lanerooftop solar | rooftop solar | 1 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | Ashfield | 5.8 |
| Two Oaks Quarrysolar farm | solar farm | 5 | permission expiredupdated Aug 2020 | Sep 2015 | granted Oct 2015 | Aug 2020 | Ashfield | 5.9 |
| Rufford Solar Farmsolar farm | solar farm | 5 | refusedupdated Dec 2015 | Sep 2015 | refused Dec 2015 | Dec 2015 | Newark and Sherwood | 7.1 |
| Two Oaks Quarry, Coxmoor Roadsolar farm | solar farm | 3.8 | approved, not builtupdated Feb 2024 | Nov 2022 | granted Jan 2024 | Feb 2024 | Ashfield | 7.3 |
| Losk Lanewind farm | wind farm | 5 | refusedupdated Feb 2013 | Oct 2010 | refused Feb 2013 | Feb 2013 | Bolsover | 7.9 |
| Welbeck Collierysolar farm | solar farm | 11.3 | operationalupdated Sep 2018 | Nov 2012 | granted Feb 2013 | Sep 2018 | Mansfield | 8.1 |
| Whiteborough Farmsolar farm | solar farm | 2.2 | abandonedupdated Jun 2019 | Aug 2015 | granted Feb 2016 | Jun 2019 | Ashfield | 8.2 |
| Stockley Hill Solar Farmsolar farm | solar farm | 5 | refusedupdated Mar 2015 | Oct 2015 | refused Feb 2016 | Mar 2015 | Bolsover | 8.3 |
| Newton Wood Farmbattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Mar 2025 | May 2020 | granted Oct 2020 | Mar 2025 | Bolsover | 8.6 |
| Fulwood Grange Farmsolar farm | solar farm | 5 | abandonedupdated May 2020 | Jul 2015 | granted Nov 2015 | May 2020 | Ashfield | 8.6 |
| Warren Housesolar farm | solar farm | 4 | refusedupdated Nov 2015 | Oct 2015 | refused Jan 2016 | Nov 2015 | Ashfield | 8.8 |
| Hurst Farm, Mansfield Roadbattery storage | battery storage | 99.9 | approved, not builtupdated Jan 2026 | Jul 2025 | granted Dec 2025 | Jan 2026 | Bolsover | 8.8 |
| Crow Trees Farmsolar farm | solar farm | 4.7 | operationalupdated Sep 2018 | Apr 2014 | granted Jun 2014 | Sep 2018 | Ashfield | 9.0 |
| Twin Yards Solar Farmsolar farm | solar farm | 5 | operationalupdated Oct 2017 | Jul 2015 | granted Sep 2015 | Oct 2017 | Bolsover | 9.5 |
| Inkersall Grange Farmsolar farm | solar farm | 49.9 | operationalupdated Jul 2026 | Jul 2019 | granted Sep 2019 | Jul 2026 | Newark and Sherwood | 9.5 |
| Newstead and Annesley Wind Turbinewind turbine | wind turbine | 1.5 | operationalupdated Apr 2017 | Oct 2014 | granted Oct 2015 | Apr 2017 | Gedling | 9.6 |
| Land at Bolsover Moor Quarrysolar farm | solar farm | 5 | operationalupdated May 2017 | Jul 2015 | granted Sep 2015 | May 2017 | Bolsover | 9.6 |
| Frithwood Farm, Frithwood Lane Solar Farmsolar farm | solar farm | 25 | approved, not builtupdated Dec 2023 | Jan 2023 | granted Dec 2023 | Dec 2023 | Bolsover | 9.8 |
| Land South Off Ollerton Roadsolar farm | solar farm | 4.2 | operationalupdated Mar 2017 | May 2015 | granted Jun 2016 | Mar 2017 | Newark and Sherwood | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Unit A, Concorde Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Mansfield | 1.5 |
| The Samworth Church Academy, Sherwood Hall Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Mansfield | 2.3 |
| Sutton Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Mansfield | 3.3 |
| Kestral Roadbattery storage | battery storage | — | approved, not builtupdated Dec 2023 | Aug 2023 | granted Dec 2023 | Dec 2023 | Mansfield | 3.5 |
| Crown Farm Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Oct 2022 | Mar 2022 | Mansfield | 3.6 |
| Mcdonalds, Mansfield Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | May 2026 | — | — | Ashfield | 4.0 |
| Linney Group, Adamswayrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Mansfield | 4.4 |
| Crabtree Lane, Skegbybattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Oct 2024 | granted Jun 2025 | Jul 2025 | Ashfield | 5.3 |
| Lammas Leisure Centre, Lammas Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Dec 2024 | granted Jan 2025 | May 2025 | Ashfield | 6.0 |
| Lamtek Limited, Wolsey Driverooftop solar | rooftop solar | 0.8 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Ashfield | 6.3 |
| Brookside Way, Huthwaite Solar Photovoltaicsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2024 | Apr 2024 | granted May 2024 | Jun 2024 | Ashfield | 8.5 |
Distance from the average position of the NG19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 22 | 0 | 3 | 9 | 6 | 74.2 |
| Rooftop solar | 10 | 0 | 10 | 0 | 0 | 6.7 |
| Wind farm | 3 | 0 | 0 | 1 | 2 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 5 | 1 | 4 | 0 | 0 | 150 |
MW in pipeline: pending, approved and under-construction capacity.
How Mansfield decides solar, wind and battery applications
| Applications | Mansfield | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 3 (20%) | 19% |
| Solar refused | 3 of 14 | 12% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 13.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG19, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.