Inkersall Grange Farm (49.9 MW solar farm)

Inkersall Grange Farm is a 49.9 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2025; the record was last updated on 10 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
10 July 2026record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
1 July 2019Application submitted
26 September 2019Planning permission granted
1 May 2025Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
10 July 2026
Operator or applicant
Nextpower Inkersall Limited
Planning authority
Newark and Sherwood
Planning application reference
19/01165/FULM
Site area
80.0 ha
Address (REPD)
Inkersall Grange Farm, Inkersall Grange Road, Bilsthorpe, Newark, Nottinghamshire
Council area (by location)
Newark and Sherwood
Time to decision
12 weeks
Contracts for Difference
AR4
REPD reference
7223

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bilsthorpe (Land off Forest Lane)solar farm5operational1.6
Rufford Solar Farmsolar farm5refused2.7
Stonish Hill (Bilsthorpe)wind farm10.3operational4.3
Eakring Solar Farmsolar farm11.9operational4.5
Lindhurst Wind Farmwind farm15operational5.8
Winkburn Estate Solar Farmsolar farm49.9under construction7.0
Two Oaks Quarrysolar farm5permission expired9.2
Cotmoor Lanesolar farm49.9approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1284, -1.066).