Energy Projects Near You

Solar, wind and battery projects near Mansfield (NG18)

40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG18 (Mansfield): 2 are waiting for a planning decision, 17 approved but not yet running, 9 operational. The largest live scheme is Hurst Farm, Mansfield Road (99.9 MW battery storage, approved on 19 December 2025, not yet built), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40projects within 10 km
2awaiting a decision
17approved, not running
9operational

Projects within 10 km of NG18

Projects of 1 MW and more (28)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sherwood Way Southrooftop solarrooftop solar2.7approved, not built may be out of dateupdated Sep 2021Jun 2021granted Sep 2021Sep 2021Ashfield2.7
Lindhurst Wind Farmwind farmwind farm15operationalupdated Dec 2010Jun 2006granted Sep 2007Dec 2010Newark and Sherwood3.1
Hamilton Road Solar Farmsolar farmsolar farm7refusedupdated May 2026Jul 2025refused Mar 2026May 2026Ashfield3.2
Land At Debdale Lanesolar farmsolar farm5operationalupdated Aug 2016Jul 2015granted Oct 2015Aug 2016Mansfield3.3
Two Oaks Quarrysolar farmsolar farm5permission expiredupdated Aug 2020Sep 2015granted Oct 2015Aug 2020Ashfield3.5
Ashland Solar Farmsolar farmsolar farm5permission expiredupdated Jul 2020Aug 2015granted Nov 2015Jul 2020Ashfield3.6
Penniment House Farm/Water Lane Farmsolar farmsolar farm4refusedupdated May 2016Feb 2016refused May 2016May 2016Mansfield4.1
Romo, Oddicroft Lanerooftop solarrooftop solar1approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Ashfield4.8
Littlewood Lane Solarsolar farmsolar farm5operationalupdated May 2017Aug 2015granted Nov 2015May 2017Bolsover5.0
Two Oaks Quarry, Coxmoor Roadsolar farmsolar farm3.8approved, not builtupdated Feb 2024Nov 2022granted Jan 2024Feb 2024Ashfield5.0
Rufford Solar Farmsolar farmsolar farm5refusedupdated Dec 2015Sep 2015refused Dec 2015Dec 2015Newark and Sherwood5.3
Land West Of Sookholme Roadsolar farmsolar farm10refusedupdated Jun 2016Sep 2015refused Jun 2016Jun 2016Mansfield6.2
Warren Housesolar farmsolar farm4refusedupdated Nov 2015Oct 2015refused Jan 2016Nov 2015Ashfield6.8
Newstead and Annesley Wind Turbinewind turbinewind turbine1.5operationalupdated Apr 2017Oct 2014granted Oct 2015Apr 2017Gedling7.3
SPF Thirty Acres Farmsolar farmsolar farm3.8operationalupdated Jul 2016Jul 2015granted Nov 2015Jul 2016Mansfield7.6
Brecks Solar Farmsolar farmsolar farm45.4approved, not builtupdated Feb 2026May 2023granted Sep 2023Feb 2026Mansfield7.7
Inkersall Grange Farmsolar farmsolar farm49.9operationalupdated Jul 2026Jul 2019granted Sep 2019Jul 2026Newark and Sherwood7.9
Fulwood Grange Farmsolar farmsolar farm5abandonedupdated May 2020Jul 2015granted Nov 2015May 2020Ashfield8.1
Roseland Community Wind Farmwind farmwind farm12refusedupdated Mar 2015Apr 2012refused Jul 2013Mar 2015Bolsover8.3
Crow Trees Farmsolar farmsolar farm4.7operationalupdated Sep 2018Apr 2014granted Jun 2014Sep 2018Ashfield8.4
Whiteborough Farmsolar farmsolar farm2.2abandonedupdated Jun 2019Aug 2015granted Feb 2016Jun 2019Ashfield8.8
Two Dales Farmsolar farmsolar farm4refusedupdated May 2016Jul 2015refused Mar 2016May 2016Ashfield9.1
Newton Wood Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Mar 2025May 2020granted Oct 2020Mar 2025Bolsover9.2
Former Langton Colliery Sitesolar farmsolar farm5.7permission expiredupdated Sep 2019Mar 2016granted Jun 2016Sep 2019Ashfield9.3
Twin Yards Solar Farmsolar farmsolar farm5operationalupdated Oct 2017Jul 2015granted Sep 2015Oct 2017Bolsover9.4
Bilsthorpe (Land off Forest Lane)solar farmsolar farm5operationalupdated Jul 2017Aug 2015granted Jan 2016Jul 2017Newark and Sherwood9.6
Featherstone House Farmsolar farmsolar farm3.2approved, not built may be out of dateupdated Oct 2018Aug 2013granted Apr 2016Oct 2018Newark and Sherwood9.6
Hurst Farm, Mansfield Roadbattery storagebattery storage99.9approved, not builtupdated Jan 2026Jul 2025granted Dec 2025Jan 2026Bolsover9.7
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Samworth Church Academy, Sherwood Hall Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Mansfield1.4
Linney Group, Adamswayrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Mansfield2.0
Kestral Roadbattery storagebattery storage—approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Mansfield2.2
Sutton Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2022Feb 2022granted Mar 2022Mar 2022Mansfield2.7
Crown Farm Wayrooftop solarrooftop solar0.3approved, not builtupdated Mar 2022Feb 2022granted Oct 2022Mar 2022Mansfield2.8
Mcdonalds, Mansfield Road - Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Ashfield3.5
Unit A, Concorde Wayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Mansfield3.5
Lamtek Limited, Wolsey Driverooftop solarrooftop solar0.8approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Ashfield5.1
Lammas Leisure Centre, Lammas Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Jan 2025May 2025Ashfield5.7
Crabtree Lane, Skegbybattery storagebattery storage—approved, not builtupdated Jul 2025Oct 2024granted Jun 2025Jul 2025Ashfield5.8
Brookside Way, Huthwaite Solar Photovoltaicsrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024Ashfield8.4
Eurocell Nickel, High View Roadrooftop solarrooftop solar0.6application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Bolsover9.8

Distance from the average position of the NG18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm21037652.4
Rooftop solar11110007.3
Wind farm200110
Wind turbine100100
Battery storage51400150

MW in pipeline: pending, approved and under-construction capacity.

How Mansfield decides solar, wind and battery applications

ApplicationsMansfieldUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused3 of 1412%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Mansfield

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG18, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.