Hamilton Road Solar Farm (7 MW)

Hamilton Road Solar Farm is a 7 MW solar farm project in Ashfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 March 2026; the record was last updated on 7 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
refusedstatus in REPD
7 May 2026record last updated
Ashfieldcouncil area

Planning timeline

DateStage
4 July 2025Application submitted
18 March 2026Refused by the planning authority

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
refused
Record last updated
7 May 2026
Operator or applicant
Hamilton Solar Limited
Planning authority
Ashfield
Planning application reference
V/2025/0412
Site area
7.3 ha
Address (REPD)
Hamilton Hill Farm, Cauldwell Road, Sutton In Ashfield
Council area (by location)
Ashfield
Time to decision
37 weeks
Name in REPD
Hamilton Road - Solar Farm
REPD reference
20136

Earlier applications for this site

ApplicationMWSubmittedOutcome
Hamilton Road Solar Farm V/2022/0562726 July 2022refused 12 December 2022

Who decides

ApplicationsAshfieldUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused4 of 1812%
Battery storage refused0 of 116%
Median time from submission to decision15.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ashland Solar Farmsolar farm5permission expired2.4
Two Oaks Quarrysolar farm5permission expired2.5
Land At Debdale Lanesolar farm5operational4.1
Fulwood Grange Farmsolar farm5abandoned4.9
Lindhurst Wind Farmwind farm15operational5.0
Former Langton Colliery Sitesolar farm5.7permission expired6.1
Twin Yards Solar Farmsolar farm5operational6.4
Littlewood Lane Solarsolar farm5operational6.6
Newton Wood Farmbattery storage49.9approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1236, -1.2258).