Two Oaks Quarry (5 MW solar farm)

Two Oaks Quarry is a 5 MW solar farm project in Ashfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 15 October 2018; the record was last updated on 11 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
11 August 2020record last updated
Ashfieldcouncil area

Planning timeline

DateStage
30 September 2015Application submitted
15 October 2015Planning permission granted
15 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
11 August 2020
Operator or applicant
Mansfield Sand
Planning authority
Ashfield
Planning application reference
V/2015/0589
Address (REPD)
Two Oaks Quarry, Derby Road, Coxmoor Road, Kirkby in Ashfield, Mansfield
Council area (by location)
Ashfield
Time to decision
2 weeks
REPD reference
5840

Who decides

ApplicationsAshfieldUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused4 of 1812%
Battery storage refused0 of 116%
Median time from submission to decision15.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hamilton Road Solar Farmsolar farm7refused2.5
Lindhurst Wind Farmwind farm15operational3.4
Ashland Solar Farmsolar farm5permission expired4.8
Land At Debdale Lanesolar farm5operational6.0
Fulwood Grange Farmsolar farm5abandoned6.5
Rufford Solar Farmsolar farm5refused6.6
Former Langton Colliery Sitesolar farm5.7permission expired7.0
Littlewood Lane Solarsolar farm5operational8.2
Twin Yards Solar Farmsolar farm5operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1075, -1.199).