Energy Projects Near You

Solar, wind and battery projects near Nottingham (NG15)

37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG15 (Ashfield): 3 are waiting for a planning decision, 23 approved but not yet running, 4 operational. The largest live scheme is Long Lane Solar Farm / Nottingham Brick Works (17 MW solar farm, under construction since 15 July 2016), 3.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37projects within 10 km
3awaiting a decision
23approved, not running
4operational

Projects within 10 km of NG15

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
ITP Aero, Harrier Parkrooftop solarrooftop solar1.9approved, not builtupdated May 2025Nov 2024granted Dec 2024May 2025Ashfield2.9
Newstead and Annesley Wind Turbinewind turbinewind turbine1.5operationalupdated Apr 2017Oct 2014granted Oct 2015Apr 2017Gedling3.5
Long Lane Solar Farm / Nottingham Brick Workssolar farmsolar farm17under constructionupdated Dec 2019Jul 2015granted Nov 2015Dec 2019Broxtowe3.7
Warren Housesolar farmsolar farm4refusedupdated Nov 2015Oct 2015refused Jan 2016Nov 2015Ashfield4.8
Two Dales Farmsolar farmsolar farm4refusedupdated May 2016Jul 2015refused Mar 2016May 2016Ashfield5.3
Two Oaks Quarry, Coxmoor Roadsolar farmsolar farm3.8approved, not builtupdated Feb 2024Nov 2022granted Jan 2024Feb 2024Ashfield5.7
Land south of Ramsdale Park Golf Coursesolar farmsolar farm4abandonedupdated Nov 2018Oct 2015granted Aug 2016Nov 2018Gedling5.8
Two Oaks Quarrysolar farmsolar farm5permission expiredupdated Aug 2020Sep 2015granted Oct 2015Aug 2020Ashfield7.0
Newthorpe Wind Turbinewind turbinewind turbine2.5operationalupdated Apr 2014Dec 2010granted Jul 2011Apr 2014Broxtowe8.1
Former Langton Colliery Sitesolar farmsolar farm5.7permission expiredupdated Sep 2019Mar 2016granted Jun 2016Sep 2019Ashfield8.3
Romo, Oddicroft Lanerooftop solarrooftop solar1approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Ashfield8.6
Lindhurst Wind Farmwind farmwind farm15operationalupdated Dec 2010Jun 2006granted Sep 2007Dec 2010Newark and Sherwood8.8
Hamilton Road Solar Farmsolar farmsolar farm7refusedupdated May 2026Jul 2025refused Mar 2026May 2026Ashfield8.9
Sherwood Way Southrooftop solarrooftop solar2.7approved, not built may be out of dateupdated Sep 2021Jun 2021granted Sep 2021Sep 2021Ashfield9.3
Crow Trees Farmsolar farmsolar farm4.7operationalupdated Sep 2018Apr 2014granted Jun 2014Sep 2018Ashfield9.4
Fulwood Grange Farmsolar farmsolar farm5abandonedupdated May 2020Jul 2015granted Nov 2015May 2020Ashfield9.5
Smaller schemes under 1 MW, mostly rooftop solar (21)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hucknall Leisure Centre, Linby Roadrooftop solarrooftop solar—approved, not builtupdated May 2025Aug 2023granted Feb 2025May 2025Ashfield0.5
Watnall Road, Hucknall - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Ashfield3.4
Blenheim Park Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Jan 2025May 2025Ashfield3.9
Bulwell Academy, Squires Avenuerooftop solarrooftop solar0.1approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Nottingham4.2
Aspect Business Parkrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Nottingham4.3
Sainsburys Supermarket, Greens Lanerooftop solarrooftop solar0.3application submittedMay 2026——Broxtowe6.3
Arnold Hill Spencer Academyrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Gedling7.7
Lamtek Limited, Wolsey Driverooftop solarrooftop solar0.8approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Ashfield7.9
Bluecoat Beechdale Academy, Harvey Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Nottingham8.7
Plymouth Avenue, Pinxtonbattery storagebattery storage0.2approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Bolsover8.7
David Lloyd Tennis And Fitness Club, Aspley Lanerooftop solarrooftop solar—approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025Nottingham8.7
Harvey Hadden Sports Village, Wigman Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Jan 2025granted Feb 2025Feb 2025Nottingham8.7
Wharf Road & Beaufit Lane, Pinxton - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Bolsover8.9
Aldercar Infant & Nursery School, Godkin Driverooftop solarrooftop solar0.4approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Amber Valley9.3
Factory Tencate Advanced Composites Limited, Amber Driverooftop solarrooftop solar0.5approved, not built may be out of dateupdated Feb 2023Oct 2022granted Dec 2022Feb 2023Amber Valley9.3
Ambulance Station, Beechdale Roadrooftop solarrooftop solar0.1approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Nottingham9.3
Kestral Roadbattery storagebattery storage—approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Mansfield9.6
Hadden Court, Glaisdale Parkwayrooftop solarrooftop solar0.3approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Nottingham9.6
Glaisdale Point, Units 10 To 12 - Roof Mounted Solar PV Arrayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Oct 2024granted Feb 2025Feb 2025Nottingham9.6
Mcdonalds, Mansfield Road - Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Ashfield9.9
Linney Group, Adamswayrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Mansfield9.9

Distance from the average position of the NG15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10021320.8
Rooftop solar19118009.9
Wind farm100100
Wind turbine200200
Battery storage523000.8

MW in pipeline: pending, approved and under-construction capacity.

How Ashfield decides solar, wind and battery applications

ApplicationsAshfieldUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused4 of 1812%
Battery storage refused0 of 116%
Median time from submission to decision15.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Ashfield

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG15, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.