Energy Projects Near You

Solar, wind and battery projects near Nottingham (NG5)

51 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG5 (Nottingham): 6 are waiting for a planning decision, 33 approved but not yet running, 8 operational. The largest live scheme is Burton Wood Farm, Spring Lane (320 MW battery storage, approved on 27 March 2025, not yet built), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51projects within 10 km
6awaiting a decision
33approved, not running
8operational

Projects within 10 km of NG5

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land south of Ramsdale Park Golf Coursesolar farmsolar farm4abandonedupdated Nov 2018Oct 2015granted Aug 2016Nov 2018Gedling4.0
Gedling Solar Farmsolar farmsolar farm5.7operationalupdated Sep 2018Nov 2012granted Oct 2013Sep 2018Gedling4.2
Burton Wood Farm, Spring Lanebattery storagebattery storage320approved, not builtupdated Mar 2026May 2024granted Mar 2025Mar 2026Gedling4.9
ITP Aero, Harrier Parkrooftop solarrooftop solar1.9approved, not builtupdated May 2025Nov 2024granted Dec 2024May 2025Ashfield5.6
Long Lane Solar Farm / Nottingham Brick Workssolar farmsolar farm17under constructionupdated Dec 2019Jul 2015granted Nov 2015Dec 2019Broxtowe6.3
Stoke Bardolph Farmwind farmwind farm3.4refusedupdated May 2012Apr 2010refused Apr 2012May 2012Gedling7.1
Severn Trent Water - Stoke Bardolph Wind Turbinewind turbinewind turbine1.5operationalupdated Dec 2015Dec 2012granted Sep 2013Dec 2015Gedling7.1
Enva, Colwickrooftop solarrooftop solar1application withdrawnupdated May 2025Apr 2025—May 2025Gedling7.4
ENVA England, Road Number 4rooftop solarrooftop solar1approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Gedling7.4
Boots Campus - Roof Top Solar Farmrooftop solarrooftop solar6.3approved, not built may be out of dateupdated Jul 2022Jun 2022granted Dec 2022Jul 2022Nottingham8.2
Nottingham University Windwind farmwind farm5refusedupdated Apr 2013Aug 2011refused Feb 2013Apr 2013Nottingham8.6
Radcliffe Road, Holme Pierrepont Solar Farmsolar farmsolar farm4.2approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023Rushcliffe8.6
Radcliffe Solar Farmsolar farmsolar farm4.2operationalupdated Aug 2015Jun 2014granted Nov 2014Aug 2015Rushcliffe8.9
Moto Hospitality, Trowell Services Area North Solar Farm & Batterysolar farmsolar farm16.1application submittedupdated May 2025Feb 2025—May 2025Broxtowe9.2
Newstead and Annesley Wind Turbinewind turbinewind turbine1.5operationalupdated Apr 2017Oct 2014granted Oct 2015Apr 2017Gedling10.0
Smaller schemes under 1 MW, mostly rooftop solar (36)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Arnold Hill Spencer Academyrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Gedling1.7
Bulwell Academy, Squires Avenuerooftop solarrooftop solar0.1approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Nottingham3.6
David Lloyd Tennis And Fitness Club, Aspley Lanerooftop solarrooftop solar—approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025Nottingham4.3
Aspect Business Parkrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Nottingham4.6
Nottingham Trent University, Maudslayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Nottingham4.7
Ambulance Station, Beechdale Roadrooftop solarrooftop solar0.1approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Nottingham5.2
Nottingham One, Canal Street- Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Nottingham5.4
Madison Court, Derwent Wayrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Nottingham5.5
Blenheim Park Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Jan 2025May 2025Ashfield5.5
Watnall Road, Hucknall - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Ashfield5.6
Bluecoat Beechdale Academy, Harvey Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Nottingham5.7
Eastcroft Municipal Depotbattery storagebattery storage0.6operationalupdated Mar 2023——Mar 2023Nottingham5.7
Eastcroft Municipal Depotsolar farmsolar farm0.2operationalupdated Mar 2023——Mar 2023Nottingham5.7
Harvey Hadden Sports Village, Wigman Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Jan 2025granted Feb 2025Feb 2025Nottingham6.0
Hucknall Leisure Centre, Linby Roadrooftop solarrooftop solar—approved, not builtupdated May 2025Aug 2023granted Feb 2025May 2025Ashfield6.1
Trent Basin Community Batterybattery storagebattery storage0.5operationalupdated May 2019Dec 2016—May 2019Nottingham6.2
Colwick Loop Road, Colwickrooftop solarrooftop solar0.8approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Gedling6.4
Games Workshop Euro Hub, Willow Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Nottingham6.6
Willow Roadrooftop solarrooftop solar0.3operationalupdated Jan 2022Jun 2021granted Feb 2023Jan 2022Nottingham6.7
Pintail House, Pintail Closerooftop solarrooftop solar0.4approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Gedling6.8
Hadden Court, Glaisdale Parkwayrooftop solarrooftop solar0.3approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Nottingham7.0
Glaisdale Point, Units 10 To 12 - Roof Mounted Solar PV Arrayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Oct 2024granted Feb 2025Feb 2025Nottingham7.0
Lenton Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Nottingham7.1
Lenton Lanerooftop solarrooftop solar0.2application submittedupdated Aug 2024Aug 2024—Aug 2024Nottingham7.1
Enviro Building, Colwickrooftop solarrooftop solar0.3approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Gedling7.4
Redfield Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Nottingham7.5
Sainsburys Supermarket, Greens Lanerooftop solarrooftop solar0.3application submittedMay 2026——Broxtowe7.5
Sytner Group, Abbeyfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Nottingham7.6
JK Foods UK, Bull Close Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Nottingham7.7
Makro Booker Wholesale, The Midwayrooftop solarrooftop solar0.3approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025Nottingham7.8
David Lloyd Leisure Health and Fitness Club, Rugby Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Rushcliffe8.0
Rushcliffe arena, Rugby Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Rushcliffe8.2
Rushcliffe School, Boundary Roadrooftop solarrooftop solar—approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Rushcliffe9.0
JJ Foodservice, Lilac Groverooftop solarrooftop solar0.4application submittedMay 2026——Broxtowe9.1
Moto Hospitality, Trowell Services Area North Solar Farm & Batterybattery storagebattery storage—application submittedupdated May 2025Feb 2025—May 2025Broxtowe9.2
Heart Internet, Beeston Business Parkrooftop solarrooftop solar0.6approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Broxtowe9.8

Distance from the average position of the NG5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7123037.3
Rooftop solar353301017.2
Wind farm200020
Wind turbine200200
Battery storage52120320

MW in pipeline: pending, approved and under-construction capacity.

How Nottingham decides solar, wind and battery applications

ApplicationsNottinghamUK
Decided applications (solar, wind, battery)2010,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Median time from submission to decision8.2 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Nottingham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG5, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.