Boots Campus - Roof Top Solar Farm (6.3 MW)

Boots Campus - Roof Top Solar Farm is a 6.3 MW rooftop solar project in Nottingham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 December 2022, not yet built; the record was last updated on 8 July 2022. REPD also records that the planning permission expired on 5 December 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.3 MWrooftop solar
approved, not builtmay be out of datestatus in REPD
8 July 2022record last updated
Nottinghamcouncil area

REPD also records that the planning permission expired on 5 December 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
21 June 2022Application submitted
5 December 2022Planning permission granted
5 December 2025Permission expired

Project details

Technology
rooftop solar
Capacity
6.3 MW
Status (REPD)
approved, not built
Record last updated
8 July 2022
Operator or applicant
Boots Company Plc
Planning authority
Nottingham
Planning application reference
22/01231/PFUL3
Site area
37.5 ha
Address (REPD)
Boots Campus, D90 Building Head Office Thane Road Nottingham Nottingham City
Council area (by location)
Nottingham
Time to decision
24 weeks
REPD reference
11617

Who decides

ApplicationsNottinghamUK
Decided applications (solar, wind, battery)2010,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Median time from submission to decision8.2 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nottingham University Windwind farm5refused0.7
Southfields Farm, Common Lanebattery storage130approved, not built4.6
Fair Oaks Renewable Energy Park Solar farm & Battery energy storagesolar farm49.9approved, not built5.5
Gothambattery storage100application submitted6.2
Moto Hospitality, Trowell Services Area North Solar Farm & Batterysolar farm16.1application submitted6.8
Kingston Solar farmsolar farm49.9refused7.8
Ratcliffe On Soar Power Station Solar Farmsolar farm9approved, not built8.8
Stragglethorpe Road farmsolar farm5operational8.9
Highfields Farm Solar Farm & Battery Storagesolar farm42.9approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9272, -1.1839).