Nottingham University Wind (5 MW)
Nottingham University Wind is a 5 MW wind farm project in Nottingham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 February 2013; the record was last updated on 2 April 2013.
5 MWwind farm
refusedstatus in REPD
2 April 2013record last updated
Nottinghamcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 August 2011 | Application submitted |
| 25 February 2013 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 5 MW
- Status (REPD)
- refused
- Record last updated
- 2 April 2013
- Operator or applicant
- Nottingham University
- Planning authority
- Nottingham
- Planning application reference
- 11/02419/PFUL3
- Turbines
- 2
- Address (REPD)
- Grove Farm, off Thane Road
- Council area (by location)
- Nottingham
- Time to decision
- 80 weeks
- Name in REPD
- Nottingham University - Wind
- REPD reference
- 3744
Who decides
| Applications | Nottingham | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 1 (5%) | 19% |
| Solar refused | 0 of 19 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Median time from submission to decision | 8.2 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Boots Campus - Roof Top Solar Farm | rooftop solar | 6.3 | approved, not built | 0.7 |
| Fair Oaks Renewable Energy Park Solar farm & Battery energy storage | solar farm | 49.9 | approved, not built | 4.9 |
| Southfields Farm, Common Lane | battery storage | 130 | approved, not built | 5.1 |
| Gotham | battery storage | 100 | application submitted | 5.8 |
| Moto Hospitality, Trowell Services Area North Solar Farm & Battery | solar farm | 16.1 | application submitted | 7.5 |
| Kingston Solar farm | solar farm | 49.9 | refused | 7.5 |
| Stragglethorpe Road farm | solar farm | 5 | operational | 8.5 |
| Ratcliffe On Soar Power Station Solar Farm | solar farm | 9 | approved, not built | 8.7 |
| Highfields Farm Solar Farm & Battery Storage | solar farm | 42.9 | approved, not built | 9.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9228, -1.177).