Solar, wind and battery projects near Nottingham (NG2)
66 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG2 (Rushcliffe): 5 are waiting for a planning decision, 46 approved but not yet running, 10 operational. The largest live scheme is Burton Wood Farm, Spring Lane (320 MW battery storage, approved on 27 March 2025, not yet built), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NG2
Projects of 1 MW and more (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Nottingham University Windwind farm | wind farm | 5 | refusedupdated Apr 2013 | Aug 2011 | refused Feb 2013 | Apr 2013 | Nottingham | 3.1 |
| Boots Campus - Roof Top Solar Farmrooftop solar | rooftop solar | 6.3 | approved, not built may be out of dateupdated Jul 2022 | Jun 2022 | granted Dec 2022 | Jul 2022 | Nottingham | 3.4 |
| Radcliffe Road, Holme Pierrepont Solar Farmsolar farm | solar farm | 4.2 | approved, not built may be out of dateupdated Jan 2023 | Sep 2022 | granted Dec 2022 | Jan 2023 | Rushcliffe | 4.8 |
| Radcliffe Solar Farmsolar farm | solar farm | 4.2 | operationalupdated Aug 2015 | Jun 2014 | granted Nov 2014 | Aug 2015 | Rushcliffe | 5.1 |
| Enva, Colwickrooftop solar | rooftop solar | 1 | application withdrawnupdated May 2025 | Apr 2025 | — | May 2025 | Gedling | 5.4 |
| ENVA England, Road Number 4rooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jul 2025 | Jul 2025 | Gedling | 5.4 |
| Stragglethorpe Road farmsolar farm | solar farm | 5 | operationalupdated Aug 2016 | Jan 2015 | granted Dec 2015 | Aug 2016 | Rushcliffe | 5.7 |
| Cotgrave Solar Farm Batterybattery storage | battery storage | 1 | abandonedupdated Mar 2019 | Dec 2015 | — | Mar 2019 | Rushcliffe | 6.0 |
| Cotgrave solar farmsolar farm | solar farm | 4.9 | operationalupdated Mar 2016 | Jun 2014 | granted Jan 2015 | Mar 2016 | Rushcliffe | 6.0 |
| Fair Oaks Renewable Energy Park Solar farm & Battery energy storagesolar farm | solar farm | 49.9 | approved, not builtupdated May 2026 | Feb 2023 | granted Oct 2023 | May 2026 | Rushcliffe | 6.2 |
| Fair Oaks Renewable Energy Park Solar farm & Battery energy storagebattery storage | battery storage | 49.9 | approved, not builtupdated May 2026 | Feb 2023 | granted Oct 2023 | May 2026 | Rushcliffe | 6.2 |
| Land Off Mill Lanesolar farm | solar farm | 1.9 | permission expiredupdated Oct 2019 | Apr 2015 | granted Sep 2015 | Oct 2019 | Rushcliffe | 6.2 |
| Gedling Solar Farmsolar farm | solar farm | 5.7 | operationalupdated Sep 2018 | Nov 2012 | granted Oct 2013 | Sep 2018 | Gedling | 7.0 |
| Stoke Bardolph Farmwind farm | wind farm | 3.4 | refusedupdated May 2012 | Apr 2010 | refused Apr 2012 | May 2012 | Gedling | 7.6 |
| Severn Trent Water - Stoke Bardolph Wind Turbinewind turbine | wind turbine | 1.5 | operationalupdated Dec 2015 | Dec 2012 | granted Sep 2013 | Dec 2015 | Gedling | 7.6 |
| Burton Wood Farm, Spring Lanebattery storage | battery storage | 320 | approved, not builtupdated Mar 2026 | May 2024 | granted Mar 2025 | Mar 2026 | Gedling | 7.7 |
| Heron Solar Farm & Battery Storagesolar farm | solar farm | 20 | approved, not builtupdated Sep 2024 | Dec 2023 | granted Aug 2024 | Sep 2024 | Rushcliffe | 7.8 |
| Heron Solar Farm & Battery Storagebattery storage | battery storage | 20 | approved, not builtupdated Sep 2024 | Dec 2023 | granted Aug 2024 | Sep 2024 | Rushcliffe | 7.8 |
| Southfields Farm, Common Lanebattery storage | battery storage | 130 | approved, not builtupdated Sep 2024 | Nov 2022 | granted Aug 2024 | Sep 2024 | Broxtowe | 7.9 |
| Gothambattery storage | battery storage | 100 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Rushcliffe | 8.3 |
| Moto Hospitality, Trowell Services Area North Solar Farm & Batterysolar farm | solar farm | 16.1 | application submittedupdated May 2025 | Feb 2025 | — | May 2025 | Broxtowe | 9.4 |
| Highfields Farm Solar Farm & Battery Storagesolar farm | solar farm | 42.9 | approved, not built may be out of dateupdated Feb 2025 | Feb 2022 | granted Feb 2023 | Feb 2025 | Rushcliffe | 9.9 |
| Highfields Farm Solar Farm & Battery Storagebattery storage | battery storage | 8 | approved, not built may be out of dateupdated Feb 2025 | Feb 2022 | granted Feb 2023 | Feb 2025 | Rushcliffe | 9.9 |
| Old Wood Energy Parkbattery storage | battery storage | 85 | approved, not builtupdated Jun 2026 | Feb 2024 | granted Jun 2026 | Jun 2026 | Rushcliffe | 9.9 |
| Old Wood Energy Park Solar Pv Panelsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2026 | Feb 2024 | granted Jun 2026 | Jun 2026 | Rushcliffe | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (41)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Eastcroft Municipal Depotbattery storage | battery storage | 0.6 | operationalupdated Mar 2023 | — | — | Mar 2023 | Nottingham | 1.2 |
| Eastcroft Municipal Depotsolar farm | solar farm | 0.2 | operationalupdated Mar 2023 | — | — | Mar 2023 | Nottingham | 1.2 |
| David Lloyd Leisure Health and Fitness Club, Rugby Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Rushcliffe | 1.2 |
| Trent Basin Community Batterybattery storage | battery storage | 0.5 | operationalupdated May 2019 | Dec 2016 | — | May 2019 | Nottingham | 1.2 |
| Rushcliffe arena, Rugby Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Rushcliffe | 1.5 |
| Nottingham One, Canal Street- Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Nottingham | 1.6 |
| Rushcliffe School, Boundary Roadrooftop solar | rooftop solar | — | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Rushcliffe | 2.1 |
| Lenton Lanerooftop solar | rooftop solar | 0.2 | application submittedupdated Aug 2024 | Aug 2024 | — | Aug 2024 | Nottingham | 2.5 |
| Lenton Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Nottingham | 2.5 |
| Sytner Group, Abbeyfield Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 | Nottingham | 2.5 |
| Nottingham Trent University, Maudslayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Nottingham | 2.6 |
| JK Foods UK, Bull Close Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Nottingham | 2.6 |
| Games Workshop Euro Hub, Willow Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Nottingham | 2.7 |
| Redfield Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Jan 2025 | Jan 2025 | Nottingham | 2.8 |
| Willow Roadrooftop solar | rooftop solar | 0.3 | operationalupdated Jan 2022 | Jun 2021 | granted Feb 2023 | Jan 2022 | Nottingham | 2.8 |
| Makro Booker Wholesale, The Midwayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2025 | Jul 2025 | granted Sep 2025 | Oct 2025 | Nottingham | 3.1 |
| Langley House, Wheatcroft Business Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Rushcliffe | 3.6 |
| Wheatcrofts Business Park, Edwaltonrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2024 | Oct 2024 | granted Nov 2024 | Nov 2024 | Rushcliffe | 3.6 |
| Madison Court, Derwent Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | Nottingham | 3.9 |
| Monarch Education Furniturerooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jan 2024 | Jan 2024 | granted Mar 2024 | Jan 2024 | Rushcliffe | 4.3 |
| JJ Foodservice, Lilac Groverooftop solar | rooftop solar | 0.4 | application submitted | May 2026 | — | — | Broxtowe | 4.6 |
| Ambulance Station, Beechdale Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Nottingham | 4.8 |
| Frontier Agriculture, Ruddingtonrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2022 | May 2022 | granted Mar 2023 | Jun 2022 | Rushcliffe | 4.8 |
| David Lloyd Tennis And Fitness Club, Aspley Lanerooftop solar | rooftop solar | — | approved, not builtupdated Oct 2025 | Jul 2025 | granted Sep 2025 | Oct 2025 | Nottingham | 4.9 |
| Colwick Loop Road, Colwickrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Gedling | 4.9 |
| Pintail House, Pintail Closerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 | Gedling | 5.3 |
| Heart Internet, Beeston Business Parkrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Jan 2025 | Jan 2025 | Broxtowe | 5.3 |
| Enviro Building, Colwickrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jul 2025 | Jul 2025 | Gedling | 5.4 |
| Wells Agriculture Barn Farm, Flawforth Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Rushcliffe | 5.8 |
| Ideagen, Mere Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Rushcliffe | 5.9 |
| Bluecoat Beechdale Academy, Harvey Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Nottingham | 6.2 |
| Harvey Hadden Sports Village, Wigman Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Jan 2025 | granted Feb 2025 | Feb 2025 | Nottingham | 6.5 |
| Hadden Court, Glaisdale Parkwayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Nottingham | 6.7 |
| Glaisdale Point, Units 10 To 12 - Roof Mounted Solar PV Arrayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Oct 2024 | granted Feb 2025 | Feb 2025 | Nottingham | 6.7 |
| Fairham Business Park, Foresters Avenuerooftop solar | rooftop solar | 0.4 | operationalupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Rushcliffe | 6.8 |
| Arnold Hill Spencer Academyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Gedling | 7.0 |
| British Geological, Keywork Solar Panelsrooftop solar | rooftop solar | 0.6 | under constructionupdated May 2022 | Oct 2020 | granted Jan 2021 | May 2022 | Rushcliffe | 7.3 |
| Bulwell Academy, Squires Avenuerooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Nottingham | 9.0 |
| George Spencer Academy, Arthur Mee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Mar 2025 | May 2025 | Broxtowe | 9.1 |
| Moto Hospitality, Trowell Services Area North Solar Farm & Batterybattery storage | battery storage | — | application submittedupdated May 2025 | Feb 2025 | — | May 2025 | Broxtowe | 9.4 |
| Aspect Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Nottingham | 9.4 |
Distance from the average position of the NG2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 1 | 5 | 5 | 0 | 183 |
| Rooftop solar | 40 | 2 | 35 | 2 | 0 | 17.8 |
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 11 | 2 | 6 | 2 | 0 | 713 |
MW in pipeline: pending, approved and under-construction capacity.
How Rushcliffe decides solar, wind and battery applications
| Applications | Rushcliffe | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 4 of 34 | 12% |
| Battery storage refused | 3 of 9 | 16% |
| Median time from submission to decision | 23.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 4 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG2, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.