Energy Projects Near You

Gedling Solar Farm (5.7 MW)

Gedling Solar Farm is a 5.7 MW solar farm project in Gedling, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2015; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.7 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
Gedlingcouncil area

Planning timeline

DateStage
21 November 2012Application submitted
23 October 2013Planning permission granted
1 August 2014Construction started
15 March 2015Operational

Project details

Technology
solar farm
Capacity
5.7 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
Gedling
Planning application reference
2012/1335
Site area
14.5 ha
Address (REPD)
Former Gedling Colliery, Arnold Lane, Gedling, Nottinghamshire
Council area (by location)
Gedling
Time to decision
48 weeks
REPD reference
2377

Who decides

ApplicationsGedlingUK
Decided applications (solar, wind, battery)1110,236
Refused1 (9%)19%
Solar refused0 of 712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision40.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burton Wood Farm, Spring Lanebattery storage320approved, not built0.8
Stragglethorpe Road farmsolar farm5operational7.4
Heron Solar Farm & Battery Storagesolar farm20approved, not built8.4
Boots Campus - Roof Top Solar Farmrooftop solar6.3approved, not built9.7
Nottingham University Windwind farm5refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9902, -1.083).