Burton Wood Farm, Spring Lane (320 MW battery storage)

Burton Wood Farm, Spring Lane is a 320 MW battery storage project in Gedling, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 March 2025, not yet built; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

320 MWbattery storage
approved, not builtstatus in REPD
31 March 2026record last updated
Gedlingcouncil area

Planning timeline

DateStage
1 May 2024Application submitted
27 March 2025Planning permission granted
27 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
320 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Grenergy Renewables
Planning authority
Gedling
Planning application reference
2024/0269
Address (REPD)
Burton Wood Farm, Spring Lane, Lambley, Nottingham
Council area (by location)
Gedling
Time to decision
47 weeks
Name in REPD
Burton Wood Farm, Spring Lane - Battery Energy Storage
REPD reference
16085

Who decides

ApplicationsGedlingUK
Decided applications (solar, wind, battery)1110,236
Refused1 (9%)19%
Solar refused0 of 712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision40.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gedling Solar Farmsolar farm5.7operational0.8
Stragglethorpe Road farmsolar farm5operational7.5
Heron Solar Farm & Battery Storagesolar farm20approved, not built8.4
Cotmoor Lanesolar farm49.9approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.993, -1.072).