Energy Projects Near You

Solar, wind and battery projects near Nottingham (NG12)

53 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG12 (Rushcliffe): 2 are waiting for a planning decision, 36 approved but not yet running, 10 operational. The largest live scheme is Burton Wood Farm, Spring Lane (320 MW battery storage, approved on 27 March 2025, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

53projects within 10 km
2awaiting a decision
36approved, not running
10operational

Projects within 10 km of NG12

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cotgrave solar farmsolar farmsolar farm4.9operationalupdated Mar 2016Jun 2014granted Jan 2015Mar 2016Rushcliffe1.0
Cotgrave Solar Farm Batterybattery storagebattery storage1abandonedupdated Mar 2019Dec 2015—Mar 2019Rushcliffe1.3
Stragglethorpe Road farmsolar farmsolar farm5operationalupdated Aug 2016Jan 2015granted Dec 2015Aug 2016Rushcliffe1.9
Heron Solar Farm & Battery Storagesolar farmsolar farm20approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024Rushcliffe2.8
Heron Solar Farm & Battery Storagebattery storagebattery storage20approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024Rushcliffe2.8
Radcliffe Solar Farmsolar farmsolar farm4.2operationalupdated Aug 2015Jun 2014granted Nov 2014Aug 2015Rushcliffe2.9
Radcliffe Road, Holme Pierrepont Solar Farmsolar farmsolar farm4.2approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023Rushcliffe3.2
Enva, Colwickrooftop solarrooftop solar1application withdrawnupdated May 2025Apr 2025—May 2025Gedling5.0
ENVA England, Road Number 4rooftop solarrooftop solar1approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Gedling5.0
Langar Lanesolar farmsolar farm10operationalupdated Dec 2017Aug 2014granted Dec 2014Dec 2017Rushcliffe7.0
Stoke Bardolph Farmwind farmwind farm3.4refusedupdated May 2012Apr 2010refused Apr 2012May 2012Gedling7.4
Severn Trent Water - Stoke Bardolph Wind Turbinewind turbinewind turbine1.5operationalupdated Dec 2015Dec 2012granted Sep 2013Dec 2015Gedling7.4
Fair Oaks Renewable Energy Park Solar farm & Battery energy storagesolar farmsolar farm49.9approved, not builtupdated May 2026Feb 2023granted Oct 2023May 2026Rushcliffe7.6
Fair Oaks Renewable Energy Park Solar farm & Battery energy storagebattery storagebattery storage49.9approved, not builtupdated May 2026Feb 2023granted Oct 2023May 2026Rushcliffe7.6
Land Off Mill Lanesolar farmsolar farm1.9permission expiredupdated Oct 2019Apr 2015granted Sep 2015Oct 2019Rushcliffe7.6
Old Wood Energy Parkbattery storagebattery storage85approved, not builtupdated Jun 2026Feb 2024granted Jun 2026Jun 2026Rushcliffe8.2
Old Wood Energy Park Solar Pv Panelsolar farmsolar farm49.9approved, not builtupdated Jun 2026Feb 2024granted Jun 2026Jun 2026Rushcliffe8.2
Nottingham University Windwind farmwind farm5refusedupdated Apr 2013Aug 2011refused Feb 2013Apr 2013Nottingham8.3
Highfields Farm Solar Farm & Battery Storagesolar farmsolar farm42.9approved, not built may be out of dateupdated Feb 2025Feb 2022granted Feb 2023Feb 2025Rushcliffe8.6
Highfields Farm Solar Farm & Battery Storagebattery storagebattery storage8approved, not built may be out of dateupdated Feb 2025Feb 2022granted Feb 2023Feb 2025Rushcliffe8.6
Boots Campus - Roof Top Solar Farmrooftop solarrooftop solar6.3approved, not built may be out of dateupdated Jul 2022Jun 2022granted Dec 2022Jul 2022Nottingham8.9
Gedling Solar Farmsolar farmsolar farm5.7operationalupdated Sep 2018Nov 2012granted Oct 2013Sep 2018Gedling9.2
West Thorpe Church Farm, Willoughby On The Woldsbattery storagebattery storage25approved, not builtupdated Sep 2024Jan 2024granted Sep 2024Sep 2024Rushcliffe9.2
Burton Wood Farm, Spring Lanebattery storagebattery storage320approved, not builtupdated Mar 2026May 2024granted Mar 2025Mar 2026Gedling9.4
Smaller schemes under 1 MW, mostly rooftop solar (29)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Monarch Education Furniturerooftop solarrooftop solar0.9approved, not builtupdated Jan 2024Jan 2024granted Mar 2024Jan 2024Rushcliffe2.0
British Geological, Keywork Solar Panelsrooftop solarrooftop solar0.6under constructionupdated May 2022Oct 2020granted Jan 2021May 2022Rushcliffe3.7
Rushcliffe School, Boundary Roadrooftop solarrooftop solar—approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Rushcliffe4.7
Langley House, Wheatcroft Business Parkrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Rushcliffe4.8
Wheatcrofts Business Park, Edwaltonrooftop solarrooftop solar0.1approved, not builtupdated Nov 2024Oct 2024granted Nov 2024Nov 2024Rushcliffe4.8
Enviro Building, Colwickrooftop solarrooftop solar0.3approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025Gedling5.0
Frontier Agriculture, Ruddingtonrooftop solarrooftop solar0.5approved, not builtupdated Jun 2022May 2022granted Mar 2023Jun 2022Rushcliffe5.2
Wells Agriculture Barn Farm, Flawforth Lanerooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Rushcliffe5.2
Pintail House, Pintail Closerooftop solarrooftop solar0.4approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Gedling5.5
Colwick Loop Road, Colwickrooftop solarrooftop solar0.8approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Gedling5.6
Trent Basin Community Batterybattery storagebattery storage0.5operationalupdated May 2019Dec 2016—May 2019Nottingham5.9
David Lloyd Leisure Health and Fitness Club, Rugby Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Rushcliffe6.2
Rushcliffe arena, Rugby Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Rushcliffe6.3
Ideagen, Mere Wayrooftop solarrooftop solar0.1approved, not builtupdated Jul 2023May 2023granted Jun 2023Jul 2023Rushcliffe6.7
Eastcroft Municipal Depotbattery storagebattery storage0.6operationalupdated Mar 2023——Mar 2023Nottingham6.8
Eastcroft Municipal Depotsolar farmsolar farm0.2operationalupdated Mar 2023——Mar 2023Nottingham6.8
Nottingham One, Canal Street- Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Nottingham7.4
John Brooke Sawmills, Fosse Wayrooftop solarrooftop solar0.2approved, not builtupdated Oct 2025Aug 2025granted Oct 2025Oct 2025Rushcliffe7.8
Sytner Group, Abbeyfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026Nottingham8.2
JK Foods UK, Bull Close Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Nottingham8.3
Nottingham Trent University, Maudslayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Nottingham8.3
Lenton Lanerooftop solarrooftop solar0.2application submittedupdated Aug 2024Aug 2024—Aug 2024Nottingham8.4
Lenton Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Nottingham8.4
Redfield Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Nottingham8.6
Games Workshop Euro Hub, Willow Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Nottingham8.8
Makro Booker Wholesale, The Midwayrooftop solarrooftop solar0.3approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025Nottingham8.8
Willow Roadrooftop solarrooftop solar0.3operationalupdated Jan 2022Jun 2021granted Feb 2023Jan 2022Nottingham8.9
JJ Foodservice, Lilac Groverooftop solarrooftop solar0.4application submittedMay 2026——Broxtowe9.9
Madison Court, Derwent Wayrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Nottingham10.0

Distance from the average position of the NG12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm120560167
Rooftop solar292251015.2
Wind farm200020
Wind turbine100100
Battery storage90620508

MW in pipeline: pending, approved and under-construction capacity.

How Rushcliffe decides solar, wind and battery applications

ApplicationsRushcliffeUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused4 of 3412%
Battery storage refused3 of 916%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

All projects in Rushcliffe

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG12, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.