West Thorpe Church Farm, Willoughby On The Wolds (25 MW battery storage)

West Thorpe Church Farm, Willoughby On The Wolds is a 25 MW battery storage project in Rushcliffe, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 September 2024, not yet built; the record was last updated on 30 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtstatus in REPD
30 September 2024record last updated
Rushcliffecouncil area

Planning timeline

DateStage
31 January 2024Application submitted
24 September 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
30 September 2024
Operator or applicant
Integrum Renewable Energy Limited
Planning authority
Rushcliffe
Planning application reference
24/00151/FUL
Address (REPD)
West Thorpe Church Farm, Willoughby On The Wolds, Loughborough
Council area (by location)
Rushcliffe
Time to decision
34 weeks
Name in REPD
West Thorpe Church Farm, Willoughby On The Wolds - Battery Energy Storage
REPD reference
15938

Who decides

ApplicationsRushcliffeUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused4 of 3412%
Battery storage refused3 of 916%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
GDL Wymeswold Solar Farm/land off the A6006solar farm6.1operational2.4
Dalbywind farm7.2operational3.2
Old Dalby Lodge Farmsolar farm5permission expired3.4
Solar Farm at E/O Wymeswoldsolar farm49.9application submitted3.6
Wymeswold Airfieldsolar farm34operational4.0
Old Wood Energy Park Solar Pv Panelsolar farm49.9approved, not built4.0
Old Wood Energy Parkbattery storage85approved, not built4.0
Highfields Farm Solar Farm & Battery Storagesolar farm42.9approved, not built4.7
Melton Roadsolar farm5abandoned4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8271, -1.0675).