Melton Road (5 MW solar farm)

Melton Road is a 5 MW solar farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 25 January 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
25 January 2019record last updated
Charnwoodcouncil area

Planning timeline

DateStage
7 August 2015Application submitted
13 November 2015Planning permission granted
13 November 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
25 January 2019
Operator or applicant
Epsilon Solar
Planning authority
Charnwood
Planning application reference
P/15/1510/2
Site area
11.0 ha
Address (REPD)
Land South of Melton Road, Burton On The Wolds,
Council area (by location)
Charnwood
Time to decision
14 weeks
REPD reference
5583

Earlier applications for this site

ApplicationMWSubmittedOutcome
Melton Road (PV) P/14/1140/21211 June 2014refused 1 September 2014

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land South of Melton Rdsolar farm5refused0.5
Solar Farm at E/O Wymeswoldsolar farm49.9application submitted2.1
Wymeswold Airfieldsolar farm34operational2.2
GDL Wymeswold Solar Farm/land off the A6006solar farm6.1operational2.7
Old Dalby Lodge Farmsolar farm5permission expired4.1
Six Hills Solar Farmsolar farm18.7operational4.6
Dalbywind farm7.2operational4.7
West Thorpe Church Farm, Willoughby On The Woldsbattery storage25approved, not built4.9
Old Hall Solar farmsolar farm22.5approved, not built5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.786, -1.0946).