Six Hills Solar Farm (18.7 MW)

Six Hills Solar Farm is an 18.7 MW solar farm project in Melton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.7 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
Meltoncouncil area

Planning timeline

DateStage
27 June 2014Application submitted
16 October 2014Planning permission granted
16 December 2014Construction started
24 March 2015Operational

Project details

Technology
solar farm
Capacity
18.7 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Melton
Planning application reference
14/00529/FUL
Address (REPD)
Field OS 00077 And 6867 Six Hills Road Ragdale
Council area (by location)
Melton
Time to decision
16 weeks
REPD reference
2057

Who decides

ApplicationsMeltonUK
Decided applications (solar, wind, battery)1810,236
Refused2 (11%)19%
Solar refused1 of 1412%
Onshore wind refused1 of 245%
Battery storage refused0 of 216%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Old Hall Solar farmsolar farm22.5approved, not built1.0
Old Dalby Lodge Farmsolar farm5permission expired2.5
Dalbywind farm7.2operational2.9
Land South of Melton Rdsolar farm5refused4.2
Melton Roadsolar farm5abandoned4.6
Asfordby Wind Farmwind farm20.7refused on appeal5.0
GDL Wymeswold Solar Farm/land off the A6006solar farm6.1operational5.2
West Thorpe Church Farm, Willoughby On The Woldsbattery storage25approved, not built5.9
Solar Farm at E/O Wymeswoldsolar farm49.9application submitted5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7806, -1.0262).