Energy Projects Near You

Solar, wind and battery projects near Melton Mowbray (LE13)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE13 (Melton): 7 are waiting for a planning decision, 7 approved but not yet running, 3 operational. The largest live scheme is Lumiere Solar Farm (50 MW solar farm, approved on 14 May 2026, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
7awaiting a decision
7approved, not running
3operational

Projects within 10 km of LE13

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Melton Mowbray Sewage Treatment Works (Solar)solar farmsolar farm2.3abandonedupdated Dec 2015Aug 2015granted Oct 2015Dec 2015Melton1.6
Melton Mowbray Solar Farmsolar farmsolar farm4.8application withdrawnupdated Aug 2011Feb 2011—Aug 2011Melton2.7
Asfordby Business Park (1)battery storagebattery storage23.4operationalupdated Apr 2020Aug 2016granted Sep 2016Apr 2020Melton2.9
Potters~ Hill Solar Photovoltaic Arrayssolar farmsolar farm20application submittedupdated Jan 2025Oct 2024—Jan 2025Melton3.1
Land to the west of Ashfordby Business Parksolar farmsolar farm3.5operationalupdated Feb 2017Jun 2015granted Sep 2015Feb 2017Melton3.7
Welby Road Solar Farmsolar farmsolar farm5permission expiredupdated May 2020Jun 2015granted Sep 2015May 2020Melton3.7
Woodfold Lane, Brentingby Solar Farmsolar farmsolar farm45application submittedupdated Oct 2025Jul 2025—Oct 2025Melton3.9
Woodfold Lane, Brentingby Solar Farmsolar farmsolar farm12application submittedupdated Mar 2025Dec 2024—Mar 2025Melton3.9
Crown Hill Wind Farmwind farmwind farm10application withdrawnupdated Dec 2015May 2014—Dec 2015Melton3.9
Asfordby Wind Farmwind farmwind farm20.7refused on appealupdated Sep 2014Dec 2010refused Jul 2012Sep 2014Melton4.4
Freeby Lane, Green Energy Park Solar Panels & Battery Storagesolar farmsolar farm49.8application submittedupdated Mar 2025Dec 2024—Mar 2025Melton6.5
Old Hall Solar farmsolar farmsolar farm22.5approved, not builtupdated Feb 2026Jan 2024granted Sep 2024Feb 2026Melton9.0
Lumiere Solar Farmsolar farmsolar farm50approved, not builtupdated Jun 2026Nov 2024granted May 2026Jun 2026Rutland9.3
Six Hills Solar Farmsolar farmsolar farm18.7operationalupdated May 2015Jun 2014granted Oct 2014May 2015Melton9.5
Twyford, Melton Solar Farmsolar farmsolar farm10approved, not builtupdated Feb 2026Oct 2023granted Nov 2024Feb 2026Melton9.7
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Potters~ Hillbattery storagebattery storage—application submittedupdated Jan 2025Oct 2024—Jan 2025Melton3.1
Freeby Lane, Green Energy Park Solar Panels & Battery Storagebattery storagebattery storage—application submittedupdated Mar 2025Dec 2024—Mar 2025Melton6.5
Hall Farm, Klondyke Lanewind turbinewind turbine0.2application submittedMay 2026——Melton7.1
Hall Farm, Wymondham Roadrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Melton8.4
Brooksby Melton College, Hoby Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jun 2023granted Sep 2024Sep 2024Melton8.7
Lumierebattery storagebattery storage—approved, not builtupdated Jun 2026Nov 2024granted May 2026Jun 2026Rutland9.3
Melton Commercial Parkrooftop solarrooftop solar0.6approved, not builtupdated Sep 2021Jul 2021granted Sep 2021Sep 2021Melton9.9

Distance from the average position of the LE13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm124320209
Rooftop solar303000.8
Wind farm200010
Wind turbine110000.2
Battery storage421100

MW in pipeline: pending, approved and under-construction capacity.

How Melton decides solar, wind and battery applications

ApplicationsMeltonUK
Decided applications (solar, wind, battery)1810,236
Refused2 (11%)19%
Solar refused1 of 1412%
Onshore wind refused1 of 245%
Battery storage refused0 of 216%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Melton

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.