Crown Hill Wind Farm (10 MW)

Crown Hill Wind Farm is a 10 MW wind farm project in Melton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 1 October 2015; the record was last updated on 2 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
application withdrawnstatus in REPD
2 December 2015record last updated
Meltoncouncil area

Planning timeline

DateStage
12 May 2014Application submitted
1 October 2015Application withdrawn

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
application withdrawn
Record last updated
2 December 2015
Operator or applicant
Crown Hill Wind Farm Limited
Planning authority
Melton
Planning application reference
14/00397/FUL
Turbines
4
Address (REPD)
Fields OS 8300 0006 And 3400 Dalby Road Melton Mowbray
Council area (by location)
Melton
REPD reference
4555

Who decides

ApplicationsMeltonUK
Decided applications (solar, wind, battery)1810,236
Refused2 (11%)19%
Solar refused1 of 1412%
Onshore wind refused1 of 245%
Battery storage refused0 of 216%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Asfordby Business Park (1)battery storage23.4operational5.6
Twyford, Melton Solar Farmsolar farm10approved, not built5.9
Asfordby Wind Farmwind farm20.7refused on appeal6.0
Welby Road Solar Farmsolar farm5permission expired6.2
Potters~ Hill Solar Photovoltaic Arrayssolar farm20application submitted6.5
Woodfold Lane, Brentingby Solar Farmsolar farm12application submitted6.8
Woodfold Lane, Brentingby Solar Farmsolar farm45application submitted6.8
Lumiere Solar Farmsolar farm50approved, not built8.5
Old Hall Solar farmsolar farm22.5approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7316, -0.8966).