Asfordby Wind Farm (20.7 MW)

Asfordby Wind Farm is a 20.7 MW wind farm project in Melton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 March 2014; the record was last updated on 19 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
refused on appealstatus in REPD
19 September 2014record last updated
Meltoncouncil area

Planning timeline

DateStage
21 December 2010Application submitted
27 July 2012Refused by the planning authority
8 March 2014Appeal refused

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
refused on appeal
Record last updated
19 September 2014
Operator or applicant
Peel Energy
Planning authority
Melton
Planning application reference
10/00951/FUL
Appeal reference
13/00003/REF
Turbines
9
Address (REPD)
Asfordby Business Park, Melton Mowbray, Leicestershire
Council area (by location)
Melton
Time to decision
83 weeks
REPD reference
4596

Who decides

ApplicationsMeltonUK
Decided applications (solar, wind, battery)1810,236
Refused2 (11%)19%
Solar refused1 of 1412%
Onshore wind refused1 of 245%
Battery storage refused0 of 216%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Welby Road Solar Farmsolar farm5permission expired1.5
Asfordby Business Park (1)battery storage23.4operational2.0
Potters~ Hill Solar Photovoltaic Arrayssolar farm20application submitted3.3
Old Hall Solar farmsolar farm22.5approved, not built4.6
Six Hills Solar Farmsolar farm18.7operational5.0
Crown Hill Wind Farmwind farm10application withdrawn6.0
Dalbywind farm7.2operational6.6
Old Dalby Lodge Farmsolar farm5permission expired6.7
Woodfold Lane, Brentingby Solar Farmsolar farm45application submitted8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7732, -0.9525).