Energy Projects Near You

Land South of Melton Rd (5 MW solar farm)

Land South of Melton Rd is a 5 MW solar farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 January 2015; the record was last updated on 17 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
17 November 2014record last updated
Charnwoodcouncil area

Planning timeline

DateStage
4 November 2014Application submitted
9 January 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
17 November 2014
Operator or applicant
Epsilon Solar
Planning authority
Charnwood
Planning application reference
P/14/2030/2
Site area
11.0 ha
Address (REPD)
Land South of Melton Road, Burton On The Wolds, Leicestershire
Council area (by location)
Charnwood
Time to decision
9 weeks
REPD reference
4746

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Melton Roadsolar farm5abandoned0.5
Solar Farm at E/O Wymeswoldsolar farm49.9application submitted2.6
Wymeswold Airfieldsolar farm34operational2.7
GDL Wymeswold Solar Farm/land off the A6006solar farm6.1operational2.9
Old Dalby Lodge Farmsolar farm5permission expired3.9
Six Hills Solar Farmsolar farm18.7operational4.2
Dalbywind farm7.2operational4.5
Old Hall Solar farmsolar farm22.5approved, not built4.7
West Thorpe Church Farm, Willoughby On The Woldsbattery storage25approved, not built5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7832, -1.0891).