Langar Lane is a 10 MW solar farm project in Rushcliffe, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 June 2016; the record was last updated on 15 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
15 December 2017record last updated
Rushcliffecouncil area

Planning timeline

DateStage
6 August 2014Application submitted
5 December 2014Planning permission granted
5 October 2015Construction started
15 June 2016Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
15 December 2017
Operator or applicant
Kappa Solar/ OPDE
Planning authority
Rushcliffe
Planning application reference
14/01594/FUL
Site area
19.4 ha
Address (REPD)
OS Fields 6230 And 7657 Langar Lane, Colston, Bassett
Council area (by location)
Rushcliffe
Time to decision
17 weeks
REPD reference
2210

Who decides

ApplicationsRushcliffeUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused4 of 3412%
Battery storage refused3 of 916%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Heron Solar Farm & Battery Storagesolar farm20approved, not built5.3
Jericho Covert Solar Farmsolar farm49.9approved, not built7.0
Stragglethorpe Road farmsolar farm5operational7.2
Elton solar farmsolar farm5operational8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9027, -0.9508).